Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-029On track3PlanningWaterfallNot started

Training Centre e-Learning Platform

Add to watchlist

A learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.

Budget (BAC)

SAR 375K

Actual cost

SAR 15K

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 375K

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Periodic update — September 2026

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Periodic update card

Progress, status, risks and support requested

Form no.
RC-PMO-F07
Template edition
2.2
Version
V1
Form date
⁦2026-10-02⁩
Hijri
21 Rabiʻ II 1448 AH
ApprovedUPD-029-2026-09Periodic update — September 2026

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-029
Project
Training Centre e-Learning Platform
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Training & Employment Centre
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Ghada A. Al-Shahrani

1ProgressAuto-filled

From the live data: accepted deliverables, the schedule and finance on the period’s last day.

Actual progress

⁦2%⁩

+2 pts on the last period

Planned to date

⁦2%⁩

SPI

1.01

Actual cost

SAR 14.1K

Main achievements this periodFilled by the project manager

Work went to the approved plan for the period, with the due deliverables handed in.

Prefilled from the August 2026 card — edit it if it changed

2Status

Overall healthAuto-filled
On track
StageAuto-filled
Planning
Forecast finishAuto-filled
⁦2027-12-31⁩

The PM’s comment on the statusFilled by the project manager

On track, no material variance from the baseline.

Prefilled from the August 2026 card — edit it if it changed

3Risks and impedimentsAuto-filled

CodeRiskScoreOwner
No open risks
CodeImpedimentSeverity
No open impediments

4Support requested

What the project needs from leadership or the committeesFilled by the project manager

No support needed this period.

Prefilled from the August 2026 card — edit it if it changed

Includes financial supportAuto-filled
No

Approval logChain: Periodic update approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleSubmitted—⁦2026-10-02⁩ 10:37
2PMO checkMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedThe reading agrees with the schedule and finance.⁦2026-10-05⁩ 14:11
3Sponsor review & approvalTechnical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2026-10-06⁩ 09:18

Signatures

PMO check

Ghada A. Al-Shahrani

Approved⁦2026-10-05⁩

Sponsor review & approval

Eng. Turki A. Al-Anazi

Approved⁦2026-10-06⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F07 · version V1

Periodic update card

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Periodic update approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2026-10-02⁩

  1. Methodology review

    PMO check

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-10-05⁩ at ⁦14:11⁩

    The reading agrees with the schedule and finance.

  2. Technical acceptance

    Sponsor review & approval

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2026-10-06⁩ at ⁦09:18⁩

Steps that do not apply to this record

  • Financial support requested — the condition «Financial link?» does not hold

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-10-02⁩

    The card as the PM filled it

    • Prefilled from the previous period’s card and the live data

    Ghada A. Al-Shahrani

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close