Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-036On track5ClosureConstructionIn progress

Business Centre (Exit 6) Branch Rehabilitation

Add to watchlist

Branch rehabilitation in handover (snags on the fire and alarm systems).

Budget (BAC)

SAR 3.4M

Actual cost

SAR 3.2M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 3.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-02-11⁩
Hijri
23 Shaʻban 1447 AH
ApprovedCRT-036-07Finishes

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Business Centre (Exit 6) Branch Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Waleed O. Al-Juhani

1The deliverableAuto-filled

DeliverableAuto-filled
Finishes
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Bandar M. Al-Shammari
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦13%⁩
DueAuto-filled
⁦2026-01-04⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-036_3.3_v1.pdfV1Eng. Bandar M. Al-Shammari⁦2025-10-30⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Bandar M. Al-Shammari
Accepted byAuto-filled
Sarah A. Al-Qarni
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2024-022
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesSubmitted—⁦2025-10-30⁩ 13:28
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-11-02⁩ 09:24
3Inspection & technical acceptance — ownerTechnical acceptanceSarah A. Al-QarniProject ownerOn behalf of Eng. Bandar M. Al-ShammariApprovedInspected and accepted against the approved acceptance criteria.⁦2025-11-04⁩ 10:31
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-11-06⁩ 10:31
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-11-09⁩ 11:08

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-11-02⁩

Inspection & technical acceptance — owner

Sarah A. Al-Qarni

Approved⁦2025-11-04⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-11-06⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-11-09⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Bandar M. Al-Shammari on ⁦2025-10-30⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-11-02⁩ at ⁦09:24⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2025-11-04⁩ at ⁦10:31⁩ · On behalf of Eng. Bandar M. Al-Shammari (Sarah A. Al-Qarni)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-11-06⁩ at ⁦10:31⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-11-09⁩ at ⁦11:08⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-10-30⁩

    PRJ-2026-036_3.3_v1.pdf

    Eng. Bandar M. Al-Shammari

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close