PRJ-2026-036On track5ClosureConstructionIn progress

Business Centre (Exit 6) Branch Rehabilitation

Add to watchlist

Branch rehabilitation in handover (snags on the fire and alarm systems).

Budget (BAC)

SAR 3.4M

Actual cost

SAR 3.2M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 3.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦1⁩ of ⁦9⁩ mandatory documents due
  • 8 mandatory documents missing
  • 1 document in the repository

The project is in its closure stage

Once the closure & handover form is approved, the project’s documents move to the archive, read-only.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3Planning
    • Project management plan, schedule & baselineMandatory· Missing

      Planning gate G3

    • Contract or purchase orderMandatory· Missing

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Missing

      Project management plan

  4. 4Execution
    • Periodic update cards & status reportsMandatory· Missing

      Periodic update card form

    • Deliverable completion certificatesMandatory· Missing

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Missing

      Corrective plan form

  5. 5ClosureCurrent stage

Documents linked to stages and tasks

Each document is tied to its stage of the project lifecycle and to the plan activities it serves — pick an activity to open it on the schedule

Project documents1
Linked to tasks0
Tasks with documents0

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 036-D1Project plan & baselinePRJ-2026-036_1.1_v1.pdfApprovedDeliverable
  • 036-D2Monitoring & reportingPRJ-2026-036_1.2_v1.pdfApprovedDeliverable
  • 036-D3Detailed designPRJ-2026-036_2.1_v1.pdfApprovedDeliverable
  • 036-D4Permits & approvalsPRJ-2026-036_2.2_v1.pdfApprovedDeliverable
  • 036-D5Site works & excavationPRJ-2026-036_3.1_v1.pdfApprovedDeliverable
  • 036-D6StructurePRJ-2026-036_3.2_v1.pdfApprovedDeliverable
  • 036-D7FinishesPRJ-2026-036_3.3_v1.pdfApprovedDeliverable
  • 036-D8SupplyPRJ-2026-036_4.1_v1.pdfApprovedDeliverable
  • 036-D9InstallationPRJ-2026-036_4.2_v1.pdfApprovedDeliverable
  • 036-D10Testing & commissioningPRJ-2026-036_4.3_v1.pdfApprovedDeliverable
  • 036-D11Provisional acceptancePRJ-2026-036_5.1_v1.pdfApprovedDeliverable
  • 036-D12Final acceptancePRJ-2026-036_5.2_v1.pdfIn reviewDeliverable