PRJ-2026-036On track5ClosureConstructionIn progress

Business Centre (Exit 6) Branch Rehabilitation

Add to watchlist

Branch rehabilitation in handover (snags on the fire and alarm systems).

Budget (BAC)

SAR 3.4M

Actual cost

SAR 3.2M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 3.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Team & roles

1 member, about ⁦0.3⁩ full-time equivalents

Leadership

1 member

  • Eng. Waleed O. Al-JuhaniProject manager⁦30%⁩Allocated ⁦130%⁩ across all projectsA

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦5⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Sarah A. Al-QarniManage closelyEng. Bandar M. Al-ShammariManage closelyProject Management Office (PMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedUnited Buildings & Operations Co.Manage closely

Interest

Project sponsor

Sarah A. Al-Qarni

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-10-20⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Sarah A. Al-QarniProject sponsorDecisions and fundingSupportiveLeadingEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa⁦2026-10-20⁩
Eng. Bandar M. Al-ShammariProject ownerAccepts deliverables, owns benefitsSupportiveLeadingEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa⁦2026-10-23⁩
Project Management Office (PMO)GovernanceCompliance and data qualitySupportiveEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa⁦2026-10-17⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@chamber.sa⁦2026-10-14⁩
United Buildings & Operations Co.Main vendorDelivers the contracted workResistantSupportiveEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa⁦2026-10-24⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveEng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa⁦2026-09-26⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingEng. Waleed O. Al-Juhani⁦2026-11-15⁩
  • Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Waleed O. Al-Juhani⁦2026-11-03⁩
  • PMOData and indicator updatesWeeklyDashboardEng. Waleed O. Al-Juhani⁦2026-10-31⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Waleed O. Al-JuhaniAt launch

Coming up

By date

  1. 312026-10PMODashboard · Weekly
  2. 032026-11Project ownerEmail · Fortnightly
  3. 152026-11Project sponsorMeeting · Monthly