PRJ-2026-036On track5ClosureConstructionIn progress

Business Centre (Exit 6) Branch Rehabilitation

Add to watchlist

Branch rehabilitation in handover (snags on the fire and alarm systems).

Budget (BAC)

SAR 3.4M

Actual cost

SAR 3.2M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 3.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
RC-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2024-10-31⁩
Hijri
28 Rabiʻ II 1446 AH
ApprovedPRJ-2026-036Business Centre (Exit 6) Branch Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Business Centre (Exit 6) Branch Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Waleed O. Al-Juhani

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2024-10-06⁩

Baseline finish

⁦2026-10-31⁩

Forecast finish

⁦2026-11-12⁩

SPI

0.98

MilestonePlannedForecastSlip
Project plan approved⁦2025-03-11⁩⁦2025-03-24⁩+13 days
Designs approved⁦2025-07-09⁩⁦2025-07-31⁩+22 days
Build complete⁦2026-01-04⁩⁦2026-02-11⁩+38 days
Testing & acceptance complete⁦2026-07-03⁩⁦2026-08-24⁩+52 days
Final handover⁦2026-10-31⁩⁦2026-12-08⁩+38 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦3%⁩⁦2025-01-10⁩Eng. Waleed O. Al-Juhani
Monitoring & reporting⁦3%⁩⁦2025-03-11⁩Eng. Bandar M. Al-Shammari
Detailed design⁦6%⁩⁦2025-05-10⁩Eng. Bandar M. Al-Shammari
Permits & approvals⁦6%⁩⁦2025-07-09⁩Sarah A. Al-Qarni
Site works & excavation⁦13%⁩⁦2025-09-07⁩Sarah A. Al-Qarni
Structure⁦13%⁩⁦2025-11-05⁩Eng. Waleed O. Al-Juhani
Finishes⁦13%⁩⁦2026-01-04⁩Eng. Bandar M. Al-Shammari
Supply⁦11%⁩⁦2026-03-05⁩Eng. Waleed O. Al-Juhani
Installation⁦11%⁩⁦2026-05-04⁩Eng. Bandar M. Al-Shammari
Testing & commissioning⁦11%⁩⁦2026-07-03⁩Sarah A. Al-Qarni
Provisional acceptance⁦7%⁩⁦2026-09-01⁩Eng. Bandar M. Al-Shammari
Final acceptance⁦3%⁩⁦2026-10-31⁩Sarah A. Al-Qarni
Accepted with a certificate⁦97%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0045Preliminary-handover snags on the fire and alarm systems6MitigateEng. Waleed O. Al-Juhani

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Waleed O. Al-Juhani
Project ownerDeliverable status and acceptance datesFortnightlyEng. Waleed O. Al-Juhani
PMOData and indicator updatesWeeklyEng. Waleed O. Al-Juhani
BeneficiariesWhat changes and whenAt each milestoneEng. Waleed O. Al-Juhani
Team memberRoleAllocation
Eng. Waleed O. Al-JuhaniProject manager⁦30%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
Branch capacity after rehabilitation0 visitors / year4800 visitors / yearEng. Waleed O. Al-Juhani

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2024-10-31⁩ 13:22
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2024-11-03⁩ 09:54
3Technical acceptance — project ownerTechnical acceptanceEng. Bandar M. Al-ShammariProject ownerApproved—⁦2024-11-05⁩ 10:01
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-11-07⁩ 14:17
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2024-11-10⁩ 09:54
6Sponsor approvalTechnical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2024-11-12⁩ 13:22

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2024-11-03⁩

Technical acceptance — project owner

Eng. Bandar M. Al-Shammari

Approved⁦2024-11-05⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2024-11-07⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2024-11-10⁩

Sponsor approval

Sarah A. Al-Qarni

Approved⁦2024-11-12⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2024-10-31⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-11-03⁩ at ⁦09:54⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2024-11-05⁩ at ⁦10:01⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-11-07⁩ at ⁦14:17⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-11-10⁩ at ⁦09:54⁩

  5. Technical acceptance

    Sponsor approval

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2024-11-12⁩ at ⁦13:22⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-10-31⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Waleed O. Al-Juhani

  2. V1Returned for edit⁦2024-10-17⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Waleed O. Al-Juhani