Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-036On track5ClosureConstructionIn progress

Business Centre (Exit 6) Branch Rehabilitation

Add to watchlist

Branch rehabilitation in handover (snags on the fire and alarm systems).

Budget (BAC)

SAR 3.4M

Actual cost

SAR 3.2M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 3.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project weight

The weight and the relative weight in the portfolio

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Approval

Project weight

The weight and the relative weight in the portfolio

Form no.
RC-PMO-F03
Template edition
1.0
Version
V2
Form date
⁦2026-09-16⁩
Hijri
5 Rabiʻ II 1448 AH
ApprovedPRJ-2026-036Business Centre (Exit 6) Branch Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Business Centre (Exit 6) Branch Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Waleed O. Al-Juhani

1Weight and relative weightAuto-filled

Project weight score

65 of 100

Relative weight in the portfolio

⁦19.1%⁩

Portfolio

Building Rehabilitation & Sustainability Portfolio

5 projects

Its share of the portfolio’s progress

18.5 points of 54.9%

2Weight criteriaAuto-filled

Each criterion is rated 1–5 from the project’s record and multiplied by its approved weight.

CriterionRated fromWeightRatingPoints
Strategic importanceThe project’s strategic value⁦35%⁩428.0
Budget sizeApproved budget (BAC)⁦25%⁩315.0
Impact on members & beneficiariesThe project’s alignment score⁦20%⁩416.0
Complexity & riskThe project’s risk score⁦10%⁩12.0
Project classificationThe project’s classification⁦10%⁩24.0
Weight score—⁦100%⁩—65

3Relative weights across the portfolioAuto-filled

Proposed and cancelled projects are left out; suspended ones keep their frozen progress.

ProjectScoreRelative weightProgress
Converting the Current Headquarters into a Member Services Centre & Committee Rooms83⁦24.4%⁩⁦68%⁩
Solar Power for the Chamber’s Buildings & Branches71⁦20.9%⁩⁦58%⁩
Business Centre (Exit 6) Branch Rehabilitation65⁦19.1%⁩⁦97%⁩
Shaqra Branch Rehabilitation62⁦18.2%⁩⁦36%⁩
Energy Retrofit of the Chamber’s Existing Buildings (ESCO)59⁦17.4%⁩⁦6%⁩
Weighted portfolio progress—⁦100%⁩⁦54.9%⁩

Approval logChain: Project weight approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleSubmitted—⁦2026-09-16⁩ 11:32
2Weight model complianceMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-09-17⁩ 13:16
3Portfolio manager approvalTechnical acceptanceEng. Mishari K. Al-OtaibiPortfolio managerApproved—⁦2026-09-22⁩ 14:23

Signatures

Weight model compliance

Ghada A. Al-Shahrani

Approved⁦2026-09-17⁩

Portfolio manager approval

Eng. Mishari K. Al-Otaibi

Approved⁦2026-09-22⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F03 · version V2

Project weight

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project weight approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2026-09-16⁩

  1. Methodology review

    Weight model compliance

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-09-17⁩ at ⁦13:16⁩

  2. Technical acceptance

    Portfolio manager approval

    Eng. Mishari K. Al-Otaibi · Portfolio manager

    Approved · ⁦2026-09-22⁩ at ⁦14:23⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-09-14⁩

    Classification added at 10; budget cut from 35 to 25 so the building projects do not swamp the portfolio

    Dr. Noura M. Al-Otaibi

  2. V1Approved⁦2025-12-02⁩

    First model: strategic importance, budget, impact, complexity

    Dr. Noura M. Al-Otaibi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close