PRJ-2026-036On track5ClosureConstructionIn progress

Business Centre (Exit 6) Branch Rehabilitation

Add to watchlist

Branch rehabilitation in handover (snags on the fire and alarm systems).

Budget (BAC)

SAR 3.4M

Actual cost

SAR 3.2M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 3.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
RC-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2024-10-13⁩
Hijri
10 Rabiʻ II 1446 AH
ApprovedMTG-KO-036Kick-off — Business Centre (Exit 6) Branch Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Business Centre (Exit 6) Branch Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Waleed O. Al-Juhani

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Business Centre (Exit 6) Branch Rehabilitation
Date and timeAuto-filled
⁦2024-10-13⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Eng. Waleed O. Al-Juhani

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Sarah A. Al-QarniAssistant Secretary-General, Support Services
Eng. Bandar M. Al-ShammariDirector General, Facilities & General Services
Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & Maintenance
Dr. Noura M. Al-OtaibiDirector, Project Management Office

2Roles

PersonRoleDuty
Sarah A. Al-QarniProject sponsorSponsors the project, decides escalations and material changes
Eng. Bandar M. Al-ShammariProject ownerApproves the requirements and accepts the deliverables
Eng. Waleed O. Al-JuhaniProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates

3Tasks

TaskOwnerDueStatus
Project plan approvedEng. Waleed O. Al-Juhani⁦2025-03-11⁩Done
Designs approvedEng. Waleed O. Al-Juhani⁦2025-07-09⁩Done
Build completeEng. Waleed O. Al-Juhani⁦2026-01-04⁩Done
Testing & acceptance completeEng. Waleed O. Al-Juhani⁦2026-07-03⁩Done

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Committee: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-02-04⁩
Start confirmed
Sarah A. Al-Qarni · ⁦2024-10-14⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2024-10-14⁩ 14:47
2Chair’s approval (sponsor)Technical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2024-10-15⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-10-16⁩ 12:21

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2024-10-16⁩

Chair’s approval (sponsor)

Sarah A. Al-Qarni

Approved⁦2024-10-15⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2024-10-14⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-10-16⁩ at ⁦12:21⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2024-10-15⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2024-10-13⁩

    The minutes as taken

    Eng. Waleed O. Al-Juhani

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close