Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-036On track5ClosureConstructionIn progress

Business Centre (Exit 6) Branch Rehabilitation

Add to watchlist

Branch rehabilitation in handover (snags on the fire and alarm systems).

Budget (BAC)

SAR 3.4M

Actual cost

SAR 3.2M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 3.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project closure & handover

Performance, handover, open commitments and lessons learned

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Form no.
RC-PMO-F12
Template edition
2.0
Version
V0
Form date
⁦2026-10-28⁩
Hijri
17 Jumada I 1448 AH
DraftPRJ-2026-036Business Centre (Exit 6) Branch Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Business Centre (Exit 6) Branch Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Waleed O. Al-Juhani

1PerformanceAuto-filled

Approved budget

SAR 3.4M

Actual cost

SAR 3.2M

Cost variance

SAR +133K

Schedule variance

+12 days

2HandoverAuto-filled

ItemStateOwnerEvidence
Final acceptance of deliverablesOpenEng. Bandar M. Al-ShammariFinal acceptance of every deliverable
Financial settlementOpenKhalid N. Al-MutairiSpend reconciled, commitments closed
Contracts closedOpenKhalid N. Al-MutairiContracts closed, retention released
Documents archivedOpenEng. Waleed O. Al-JuhaniDocuments archived with classification
Lessons learnedOpenEng. Waleed O. Al-JuhaniLessons-learned session
Benefits handed to their ownerOpenEng. Bandar M. Al-ShammariBenefits handed to their owner with a measurement plan
Final reportOpenEng. Waleed O. Al-JuhaniFinal report and its approval
BenefitNew ownerHandover
Branch capacity after rehabilitationEng. Waleed O. Al-JuhaniPlanned

3Open commitments

CommitmentOwnerDue
Final acceptance of deliverables — Final acceptance of every deliverableEng. Bandar M. Al-Shammari⁦2026-11-02⁩
Financial settlement — Spend reconciled, commitments closedKhalid N. Al-Mutairi⁦2026-12-02⁩
Contracts closed — Contracts closed, retention releasedKhalid N. Al-Mutairi⁦2026-12-12⁩
Documents archived — Documents archived with classificationEng. Waleed O. Al-Juhani⁦2026-12-07⁩
Lessons learned — Lessons-learned sessionEng. Waleed O. Al-Juhani⁦2026-11-27⁩
Benefits handed to their owner — Benefits handed to their owner with a measurement planEng. Bandar M. Al-Shammari⁦2026-11-22⁩
Final report — Final report and its approvalEng. Waleed O. Al-Juhani⁦2026-12-17⁩

4Lessons learnedAuto-filled

  1. —

Approval logChain: Project closure & handover approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

No decisions yet — the form has not been submitted.

Signatures

Closure file completeness

Ghada A. Al-Shahrani

Later

Handover accepted — project owner

Eng. Bandar M. Al-Shammari

Later

Final financial settlement

Munirah A. Al-Khalidi

Later

Contracts closed, guarantees released

Mazen A. Al-Hazmi

Later

Project Approval Committee

Dr. Noura M. Al-Otaibi

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F12 · version V0

Project closure & handover

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project closure & handover approval · version ⁦1⁩

Not submitted for approval yet.

  1. Methodology review

    Closure file completeness

    Ghada A. Al-Shahrani · PMO — analyst

    Delegated to Dr. Noura M. Al-Otaibi

  2. Technical acceptance

    Handover accepted — project owner

    Eng. Bandar M. Al-Shammari · Project owner
  3. Financial approval

    Final financial settlement

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

  4. Financial approval

    Contracts closed, guarantees released

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee
Waiting on Eng. Waleed O. Al-Juhani

Previous versions

Every version is kept with its status and what changed.

  1. V0DraftCurrent⁦2026-10-28⁩

    The closure file in preparation

    Eng. Waleed O. Al-Juhani

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close