AI insight
The current-HQ rehabilitation holds the worst quality problems
Two open NCRs (the underground-tank leak and the chiller-base concrete) costing SAR 122K, and the project audit found no resident quality engineer on site since June.
Quality plans, inspections, non-conformance reports and corrective actions.
Of 16 raised in 2026
64% with remarks · of 22 inspections
Of 4 open actions
From raising an NCR to closing it
Rework, retests and delay — 2026
Drag a report to its next stage. It cannot go to verification without a corrective action, nor close before its actions are done and verified.
Found, not yet investigated
Space picks the card up, the arrow keys move it, Space drops it, Escape cancels.
Root-cause analysis
Space picks the card up, the arrow keys move it, Space drops it, Escape cancels.
Corrective action under way
Space picks the card up, the arrow keys move it, Space drops it, Escape cancels.
Checking the fix works
Space picks the card up, the arrow keys move it, Space drops it, Escape cancels.
Closed after verification
Space picks the card up, the arrow keys move it, Space drops it, Escape cancels.
Acceptance criteria met in each project’s plan, inspection pass rate and open NCRs — and the inspection & review calendar.
Worst first · click the criteria to open the quality plan
Scheduled for the next two weeks, and the latest results
Review of the handover file and documentation
Document review · Correspondence & Document Management System
Design review of the redesigned foundation axes
Design review · The Chamber’s Investment Building — Business Tower on King Fahd Road
Pre-launch penetration test
Security test · My Business Portal 2.0 — the Unified Member Journey
Re-test of tank 2 water-tightness
Site inspection · Converting the Current Headquarters into a Member Services Centre & Committee Rooms
MEP first fix — level 3
Site inspection · Training & Employment Centre Complex
Basement retaining-wall inspection
Site inspection · Chamber Branch & Manufacturers’ Service Centre — Second Industrial City
Backfill compaction — zone 3
Site inspection · The Chamber’s New Headquarters Building
Waterproofing of the east roof
Site inspection · Training & Employment Centre Complex
Flash test of panel batch 6
Material test · Solar Power for the Chamber’s Buildings & Branches
Acceptance test of the wave-one services
Acceptance test · My Business Portal 2.0 — the Unified Member Journey
Acceptance of fire alarm and suppression on floors 3 and 4
Site inspection · Business Centre (Exit 6) Branch Rehabilitation
AI insight
Two open NCRs (the underground-tank leak and the chiller-base concrete) costing SAR 122K, and the project audit found no resident quality engineer on site since June.
Every NCR, inspection, plan, standard and corrective action — searchable, filterable, exportable.
Display options
| Critical | Corrective action | Workmanship | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | 2026-09-18 | In 13 days2026-11-1030 Jumada I 1448 AH | SAR 90K | |
| High | Investigating | Materials | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | 2026-10-06 | In 8 days2026-11-0525 Jumada I 1448 AH | SAR 32K | |
| High | Verifying | Workmanship | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | 2026-08-27 | In 2 days2026-10-3019 Jumada I 1448 AH | SAR 46K | |
| High | Investigating | Design | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | 2026-09-12 | In 5 days2026-11-0222 Jumada I 1448 AH | SAR 38K | |
| High | Verifying | Data | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | 2026-09-05 | 3 days overdue2026-10-2514 Jumada I 1448 AH | SAR 9,000 | |
| High | Open | Workmanship | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.sa | 2026-10-27 | In 27 days2026-11-2414 Jumada II 1448 AH | SAR 21.5K | |
| Medium | Open | Materials | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesP-022s.almalki@chamber.sa | 2026-10-22 | In 22 days2026-11-199 Jumada II 1448 AH | SAR 10.5K | |
| Medium | Open | Workmanship | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsP-020a.asiri@chamber.sa | 2026-10-25 | In 18 days2026-11-155 Jumada II 1448 AH | SAR 14K | |
| Medium | Corrective action | Documentation | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | 2026-09-24 | 2 days overdue2026-10-2615 Jumada I 1448 AH | — | |
| Medium | Corrective action | Software | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, My Business Portal 2.0P-005s.alghamdi@chamber.sa | 2026-10-01 | In 6 days2026-11-0323 Jumada I 1448 AH | SAR 4,750 | |
| Total · 12 | SAR 268.8K |
What changed in the quality records in this session.
No changes on this screen yet.