Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 3
- Date
- 2025-09-05
- Hijri
- 13 Rabiʻ I 1447 AH
- Reference
- PAY-2025-023-03
Interim payment certificate no. (3)
For the work of August 2025
- Contract number
- RC/2025/023
- Supplier-portal reference
- 2504720693
- Contract
- New Premium Members Centre & VIP lounges — fit-out
- Contractor
- Coastline Contracting & Development Co.
- Contractor VAT number
- 340303951060003
- Project
- New Premium Members Centre & VIP Lounges
- Contract period
- 2025-04-06 — 2027-02-28
- Original contract value
- 5,900,000
- Current contract value
- 5,900,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 758,500 |
| 2 | Less: previous certificates | (446,500) |
| 3 | Value of work in this certificate | 312,000 |
| 4 | Less: retention (10%) | (31,200) |
| 5 | Less: advance payment recovery (10%) | (31,200) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (62,400) |
| 8 | Net before VAT | 249,600 |
| 9 | Add: value added tax (15%) | 37,440 |
| 10 | Net amount payable to the contractor | 287,040 |
Amount in words: Two hundred eighty-seven thousand forty Saudi riyals only
Retention held up to this certificate: SAR 75.9K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 413,000 | 73,750 | 48,700 | 122,450 | 30% |
| Earthworks & foundations | 1,062,000 | 114,450 | 76,700 | 191,150 | 18% |
| Concrete & structural works | 1,829,000 | 152,050 | 106,600 | 258,650 | 14% |
| Mechanical, electrical & plumbing | 1,416,000 | 73,100 | 54,350 | 127,450 | 9% |
| Finishes & external works | 885,000 | 28,900 | 22,300 | 51,200 | 6% |
| Testing & commissioning | 295,000 | 4,250 | 3,350 | 7,600 | 3% |
| Total | 5,900,000 | 446,500 | 312,000 | 758,500 | 13% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Talal H. Al-Ghamdi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Fahad T. Al-Sulami
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani