Certificate ⁦4⁩ — October 2025

New Premium Members Centre & VIP lounges — fit-out

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
4
Date
⁦2025-10-29⁩
Hijri
7 Jumada I 1447 AH
Reference
PAY-2025-023-04

Interim payment certificate no. (⁦4⁩)

For the work of October 2025

Contract number
RC/2025/023
Supplier-portal reference
2504720693
Contract
New Premium Members Centre & VIP lounges — fit-out
Contractor
Coastline Contracting & Development Co.
Contractor VAT number
340303951060003
Project
New Premium Members Centre & VIP Lounges
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
5,900,000
Current contract value
5,900,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SAR)

1Total value of work completed to date1,190,500
2Less: previous certificates(758,500)
3Value of work in this certificate432,000
4Less: retention (⁦10%⁩)(43,200)
5Less: advance payment recovery (⁦10%⁩)(43,200)
6Less: delay and breach penalties0
7Total deductions(86,400)
8Net before VAT345,600
9Add: value added tax (15%)51,840
10Net amount payable to the contractor397,440

Amount in words: Three hundred ninety-seven thousand four hundred forty Saudi riyals only

Retention held up to this certificate: SAR 119.1K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation413,000126,40065,900192,300⁦47%⁩
Earthworks & foundations1,062,000195,600104,400300,000⁦28%⁩
Concrete & structural works1,829,000258,200147,750405,950⁦22%⁩
Mechanical, electrical & plumbing1,416,000122,95077,050200,000⁦14%⁩
Finishes & external works885,00048,30032,05080,350⁦9%⁩
Testing & commissioning295,0007,0504,85011,900⁦4%⁩
Total5,900,000758,500432,0001,190,500⁦20%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Talal H. Al-Ghamdi

Al-Ghamdi⁦2025-10-29⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2025-10-31⁩

Project manager

Eng. Fahad T. Al-Sulami

Al-Sulami⁦2025-11-03⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2025-11-06⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2025-11-09⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-10-29⁩

    Eng. Talal H. Al-Ghamdi

  2. Engineer verifies quantities⁦2025-10-31⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-11-03⁩

    Eng. Fahad T. Al-Sulami · Senior Project Manager — Branches & Service Centres

    Took 3 days

  4. Payment order prepared⁦2025-11-06⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-11-09⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-04-22⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Fahad T. Al-Sulami → Dr. Abdullah S. Al-Qahtani

Certificate history

9 November 2025

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2025-11-09 13:00

6 November 2025

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2025-11-06 13:00

3 November 2025

  1. Approval: Eng. Fahad T. Al-Sulami signed “Project manager certifies”

    2025-11-03 13:00

31 October 2025

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2025-10-31 13:00

29 October 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-10-29 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close