Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-005On track4ExecutionWaterfallIn progress

Chamber Cybersecurity Programme

Add to watchlist

A security operations centre, identity and access management, and compliance with the NCA Essential Cybersecurity Controls to protect member and business data.

Budget (BAC)

SAR 1.9M

Actual cost

SAR 1.6M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 1.9M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-08-23⁩
Hijri
10 Rabiʻ I 1448 AH
ApprovedCRT-005-08System testing

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-005
Project
Chamber Cybersecurity Programme
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Yasser M. Al-Zahrani

1The deliverableAuto-filled

DeliverableAuto-filled
System testing
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Yasser M. Al-Zahrani
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦10%⁩
DueAuto-filled
⁦2026-06-22⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-005_4.1_v1.pdfV1Eng. Yasser M. Al-Zahrani⁦2026-05-09⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Nayef H. Al-Buqami
Accepted byAuto-filled
Eng. Majed S. Al-Rasheed
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Testing & acceptance complete
ContractAuto-filled
CTR-2025-004
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Yasser M. Al-ZahraniDirector, CybersecuritySubmitted—⁦2026-05-09⁩ 10:37
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-05-11⁩ 10:31
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Majed S. Al-RasheedProject ownerOn behalf of Eng. Nayef H. Al-BuqamiApprovedInspected and accepted against the approved acceptance criteria.⁦2026-05-14⁩ 11:38
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-05-17⁩ 09:24
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-05-19⁩ 10:01

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2026-05-11⁩

Inspection & technical acceptance — owner

Eng. Majed S. Al-Rasheed

Approved⁦2026-05-14⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2026-05-17⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2026-05-19⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Yasser M. Al-Zahrani on ⁦2026-05-09⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-05-11⁩ at ⁦10:31⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Nayef H. Al-Buqami · Project owner

    Approved · ⁦2026-05-14⁩ at ⁦11:38⁩ · On behalf of Eng. Nayef H. Al-Buqami (Eng. Majed S. Al-Rasheed)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-05-17⁩ at ⁦09:24⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-05-19⁩ at ⁦10:01⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-05-09⁩

    PRJ-2026-005_4.1_v1.pdf

    Eng. Yasser M. Al-Zahrani

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close