PRJ-2026-011On track3PlanningWaterfallNot started

Member 360 — Member Relationship Management on Dynamics 365

Add to watchlist

One record for every member business — its membership, transactions, enquiries, events and committees — linked to the Ministry of Commerce commercial register and the Saudi Business Center.

Budget (BAC)

SAR 1.2M

Actual cost

SAR 72K

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SAR 1.2M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-12-07⁩
Hijri
16 Jumada II 1447 AH
ApprovedDMD-2026-011Member 360 — Member Relationship Management on Dynamics 365

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-011
Project
Member 360 — Member Relationship Management on Dynamics 365
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Eng. Sami A. Al-Fraih
Project manager
Dana S. Al-Saleh

1The proposalAuto-filled

TitleAuto-filled
Member 360 — Member Relationship Management on Dynamics 365
Proposed byAuto-filled
Dana S. Al-Saleh
DepartmentAuto-filled
Enterprise Systems & Integration Department
Submitted onAuto-filled
⁦2025-12-07⁩
Proposal numberAuto-filled
DMD-2026-011

2Justification

One record for every member business — its membership, transactions, enquiries, events and committees — linked to the Ministry of Commerce commercial register and the Saudi Business Center.

3Objectives

  1. A better member experience and service quality
  2. High-quality, value-adding digital core services for members

Strategic objectives served

  • SO-2.2 — A better member experience and service quality
  • SO-2.1 — High-quality, value-adding digital core services for members

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 1.2M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 865K
Supervision & consultingSAR 165K
Internal teamSAR 110K
Contingency reserve (5%)SAR 60K
TotalSAR 1.2M

6Initial risks

RiskLevelProposed response
No initial risks recorded

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2025-12-07⁩ 10:01
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2025-12-09⁩ 14:11
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-12-10⁩ 09:18
4Portfolio manager reviewTechnical acceptanceEng. Nayef H. Al-BuqamiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-12-14⁩ 10:25
5Cost & funding reviewFinancial approvalApproval engineFinancePre-breach alert—⁦2025-12-17⁩ 08:00
6Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-12-18⁩ 10:37
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-12-23⁩ 12:39

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2025-12-09⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2025-12-10⁩

Portfolio manager review

Eng. Nayef H. Al-Buqami

Approved⁦2025-12-14⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2025-12-18⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-12-23⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Dana S. Al-Saleh on ⁦2025-12-07⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2025-12-09⁩ at ⁦14:11⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-12-10⁩ at ⁦09:18⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Nayef H. Al-Buqami · Portfolio manager

    Approved · ⁦2025-12-14⁩ at ⁦10:25⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-12-18⁩ at ⁦10:37⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-12-23⁩ at ⁦12:39⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-12-28⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Dana S. Al-Saleh

  2. V1Returned for edit⁦2025-12-07⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Dana S. Al-Saleh

Esc