PRJ-2026-011On track3PlanningWaterfallNot started

Member 360 — Member Relationship Management on Dynamics 365

Add to watchlist

One record for every member business — its membership, transactions, enquiries, events and committees — linked to the Ministry of Commerce commercial register and the Saudi Business Center.

Budget (BAC)

SAR 1.2M

Actual cost

SAR 72K

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SAR 1.2M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

0Achieved
3On track
2At risk
0Late
Average delay17 days
Jan 27Apr 27Jul 27Oct 27Jan 28
Contractual
Build completePlanned: ⁦2027-06-26⁩Forecast / actual: ⁦2027-07-12⁩Delay: 16 daysG3 +16
Executive
Project plan approvedPlanned: ⁦2026-11-04⁩Forecast / actual: ⁦2026-12-04⁩Delay: 30 daysG1 +30
Payment
Final handoverPlanned: ⁦2027-12-30⁩Forecast / actual: ⁦2028-01-04⁩Delay: 5 daysG5 +5
Regulatory
Testing & acceptance completePlanned: ⁦2027-09-27⁩Forecast / actual: ⁦2027-10-08⁩Delay: 11 daysG4 +11
Project
Designs approvedPlanned: ⁦2027-02-05⁩Forecast / actual: ⁦2027-03-02⁩Delay: 25 daysG2 +25

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-11-04⁩⁦2026-12-04⁩⁦+30⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saAt risk0Not requested
Designs approvedMS-G2Project⁦2027-02-05⁩⁦2027-03-02⁩⁦+25⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saAt risk0Not requested
Build completeMS-G3Contractual⁦2027-06-26⁩⁦2027-07-12⁩⁦+16⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saOn track0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-09-27⁩⁦2027-10-08⁩⁦+11⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saOn track0Not requested
Final handoverMS-G5Payment⁦2027-12-30⁩⁦2028-01-04⁩⁦+5⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦6%⁩

Awaiting acceptance

⁦4%⁩

Not handed in

⁦90%⁩

Deliverable flow

Pick a stage to filter the register
⁦11⁩ results
Export CSV
Project plan & baseline011-D1⁦6%⁩CRT-011-01ApprovedDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saBadr N. Al-Haqbani⁦2026-09-18⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting011-D2⁦4%⁩—SubmittedBadr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.saBadr N. Al-Haqbani⁦2026-11-04⁩V1⁦1⁩ of ⁦3⁩
Business requirements011-D3⁦8%⁩—DraftBadr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.saBadr N. Al-Haqbani⁦2026-12-21⁩V0⁦0⁩ of ⁦3⁩
Solution design011-D4⁦8%⁩—DraftEng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.saBadr N. Al-Haqbani⁦2027-02-05⁩V0⁦0⁩ of ⁦3⁩
Release 1011-D5⁦13%⁩—DraftEng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.saBadr N. Al-Haqbani⁦2027-03-24⁩V0⁦0⁩ of ⁦3⁩
Release 2011-D6⁦13%⁩—DraftDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saBadr N. Al-Haqbani⁦2027-05-10⁩V0⁦0⁩ of ⁦3⁩
Integrations011-D7⁦13%⁩—DraftBadr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.saBadr N. Al-Haqbani⁦2027-06-26⁩V0⁦0⁩ of ⁦3⁩
System testing011-D8⁦10%⁩—DraftDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saBadr N. Al-Haqbani⁦2027-08-12⁩V0⁦0⁩ of ⁦3⁩
User acceptance testing011-D9⁦10%⁩—DraftBadr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.saBadr N. Al-Haqbani⁦2027-09-27⁩V0⁦0⁩ of ⁦3⁩
Training & change011-D10⁦8%⁩—DraftBadr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.saBadr N. Al-Haqbani⁦2027-11-13⁩V0⁦0⁩ of ⁦3⁩
Go-live & handover011-D11⁦7%⁩—DraftEng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.saBadr N. Al-Haqbani⁦2027-12-30⁩V0⁦0⁩ of ⁦3⁩
Total · 11⁦100%⁩
⁦1⁩–⁦11⁩ of ⁦11⁩