Riyadh Chamber of Commerce & Industry
Project charter
Member 360 — Member Relationship Management on Dynamics 365
1Project identity
Required at this stage- Project name
- Member 360 — Member Relationship Management on Dynamics 365
- Project code
- PRJ-2026-011
- Project sponsor
- Eng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.sa
- Project manager
- Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa
- Project owner
- Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa
- Portfolio & programme
- Technology & Enterprise Systems PortfolioEnterprise Systems & Dynamics 365 Programme
- Type & methodology
- IT · Waterfall
- Current phase
- 3Planning
2Background & rationale
Required at this stageOne record for every member business — its membership, transactions, enquiries, events and committees — linked to the Ministry of Commerce commercial register and the Saudi Business Center.
3Objectives
Required at this stage- 1A better member experience and service quality
- 2High-quality, value-adding digital core services for members
4Scope
Required at this stageIn scope
- One record for every member business — its membership, transactions, enquiries, events and committees — linked to the Ministry of Commerce commercial register and the Saudi Business Center.
- Migration from legacy systems
- ERP integration
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
5High-level requirements
Required at this stage- 1Migration from legacy systems
- 2ERP integration
- 3Essential cybersecurity controls
6Deliverables
Required at this stage| 1 | Project management plan | 2026-07-27 |
| 2 | Main deliverable — stage 1 | 2027-04-08 |
| 3 | Main deliverable — final stage | 2027-10-15 |
| 4 | Final report | 2027-12-30 |
7Key milestones
Required at this stage- Charter approved2026-07-03
- Contract signed2026-09-30
- 50% of works complete2027-04-08
- Provisional acceptance2027-11-17
- Closure2027-12-30
8Budget
Required at this stage- Main contract72.1%865K
- Supervision & consulting13.8%165K
- Internal team9.2%110K
- Contingency reserve (5%)5.0%60K
9Timeline
Required at this stage10Key risks
Required at this stage- No risks recorded yet.
11Constraints
Required at this stage- Stay within the approved budget
- Comply with the Government Tenders & Procurement Law
12Assumptions
Required at this stage- Named internal staff available throughout
- Approvals land within the workflow’s action time limits
13Stakeholders
Required at this stage- Project sponsorDecisions and funding
- Project ownerAccepts deliverables, owns benefits
- Project Management Office (PMO)Governance and compliance
14Success criteria
Required at this stage- 1Delivered within the approved budget
- 2On the approved date ±5%
- 3Target benefits within 12 months
15Governance structure
Required at this stage- Change CommitteeApproves scope, cost and schedule changesWeekly
- PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
- Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly