PRJ-2026-011On track3PlanningWaterfallNot started

Member 360 — Member Relationship Management on Dynamics 365

Add to watchlist

One record for every member business — its membership, transactions, enquiries, events and committees — linked to the Ministry of Commerce commercial register and the Saudi Business Center.

Budget (BAC)

SAR 1.2M

Actual cost

SAR 72K

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SAR 1.2M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
RC-PMO-F05
Template edition
2.0
Version
V1
Form date
⁦2026-07-30⁩
Hijri
16 Safar 1448 AH
In approvalPRJ-2026-011Member 360 — Member Relationship Management on Dynamics 365

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-011
Project
Member 360 — Member Relationship Management on Dynamics 365
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Eng. Sami A. Al-Fraih
Project manager
Dana S. Al-Saleh

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2026-07-05⁩

Baseline finish

⁦2027-12-30⁩

Forecast finish

⁦2027-12-30⁩

SPI

1.00

MilestonePlannedForecastSlip
Project plan approved⁦2026-11-04⁩⁦2026-12-04⁩+30 days
Designs approved⁦2027-02-05⁩⁦2027-03-02⁩+25 days
Build complete⁦2027-06-26⁩⁦2027-07-12⁩+16 days
Testing & acceptance complete⁦2027-09-27⁩⁦2027-10-08⁩+11 days
Final handover⁦2027-12-30⁩⁦2028-01-04⁩+5 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦6%⁩⁦2026-09-18⁩Dana S. Al-Saleh
Monitoring & reporting⁦4%⁩⁦2026-11-04⁩Badr N. Al-Haqbani
Business requirements⁦8%⁩⁦2026-12-21⁩Badr N. Al-Haqbani
Solution design⁦8%⁩⁦2027-02-05⁩Eng. Sami A. Al-Fraih
Release 1⁦13%⁩⁦2027-03-24⁩Eng. Sami A. Al-Fraih
Release 2⁦13%⁩⁦2027-05-10⁩Dana S. Al-Saleh
Integrations⁦13%⁩⁦2027-06-26⁩Badr N. Al-Haqbani
System testing⁦10%⁩⁦2027-08-12⁩Dana S. Al-Saleh
User acceptance testing⁦10%⁩⁦2027-09-27⁩Badr N. Al-Haqbani
Training & change⁦8%⁩⁦2027-11-13⁩Badr N. Al-Haqbani
Go-live & handover⁦7%⁩⁦2027-12-30⁩Eng. Sami A. Al-Fraih
Accepted with a certificate⁦6%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
No risks recorded

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyDana S. Al-Saleh
Project ownerDeliverable status and acceptance datesFortnightlyDana S. Al-Saleh
PMOData and indicator updatesWeeklyDana S. Al-Saleh
BeneficiariesWhat changes and whenAt each milestoneDana S. Al-Saleh
Team memberRoleAllocation
Dana S. Al-SalehProject manager⁦20%⁩
Eng. Laila MansourIntegration adviser, Member 360 to My Business⁦35%⁩
Eng. Asma S. Al-HamdanMember 360 architecture & Ministry of Commerce / SBC links⁦30%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2026-10-23⁩ 12:33
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-10-27⁩ 14:35

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2026-10-27⁩

Technical acceptance — project owner

Badr N. Al-Haqbani

Awaiting decision

Cash flow & financial commitment

Munirah A. Al-Khalidi

Later

Sponsor approval

Eng. Sami A. Al-Fraih

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F05 · version V1

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Dana S. Al-Saleh on ⁦2026-10-23⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-10-27⁩ at ⁦14:35⁩

  2. Technical acceptance

    Technical acceptance — project owner

    Badr N. Al-Haqbani · Project owner
    2 working days leftWithin the time limit · Limit 3 working daysLimit 3 working days · Due ⁦2026-11-01⁩
    Waiting on Badr N. Al-Haqbani
  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 2 working days · Expected by ⁦2026-11-03⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Sami A. Al-Fraih · Project sponsor

    Limit 3 working days · Expected by ⁦2026-11-08⁩

Steps that do not apply to this record

  • Plan aligned with the contracts — the condition «Contract link?» does not hold

Previous versions

Every version is kept with its status and what changed.

  1. V2In approval⁦2026-07-30⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Dana S. Al-Saleh

  2. V1Returned for editCurrent⁦2026-07-16⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Dana S. Al-Saleh