PRJ-2026-011On track3PlanningWaterfallNot started

Member 360 — Member Relationship Management on Dynamics 365

Add to watchlist

One record for every member business — its membership, transactions, enquiries, events and committees — linked to the Ministry of Commerce commercial register and the Saudi Business Center.

Budget (BAC)

SAR 1.2M

Actual cost

SAR 72K

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SAR 1.2M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Periodic update cards

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Period

October 2026

Draft
Progress
⁦6%⁩
Planned
⁦6%⁩
SPI
1.00
Open the card

Periodic update cards

PeriodStatusProgressCurrent stepDate
October 2026UPD-011-2026-10Draft⁦6%⁩—⁦2026-10-26⁩
September 2026UPD-011-2026-09Approved⁦4%⁩—⁦2026-10-02⁩
August 2026UPD-011-2026-08Approved⁦2%⁩—⁦2026-09-02⁩