PRJ-2026-017At risk5ClosureWaterfallIn progress

Correspondence & Document Management System

Add to watchlist

Incoming and outgoing correspondence automated, with an archive of the chamber’s documents and its board and committee minutes.

Budget (BAC)

SAR 710K

Actual cost

SAR 675K

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 710K

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

4Achieved
0On track
0At risk
1Late
Average delay55 days
Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26
Contractual
Build completePlanned: ⁦2026-03-01⁩Forecast / actual: ⁦2026-04-28⁩Delay: 58 daysG3 +58
Executive
Project plan approvedPlanned: ⁦2025-06-07⁩Forecast / actual: ⁦2025-06-27⁩Delay: 20 daysG1 +20
Payment
Final handoverPlanned: ⁦2026-09-30⁩Forecast / actual: ⁦2026-12-24⁩Delay: 85 daysG5 +85
Regulatory
Testing & acceptance completePlanned: ⁦2026-06-15⁩Forecast / actual: ⁦2026-08-28⁩Delay: 74 daysG4 +74
Project
Designs approvedPlanned: ⁦2025-09-21⁩Forecast / actual: ⁦2025-10-27⁩Delay: 36 daysG2 +36

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-06-07⁩⁦2025-06-27⁩⁦+20⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-09-21⁩⁦2025-10-27⁩⁦+36⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-03-01⁩⁦2026-04-28⁩⁦+58⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-06-15⁩⁦2026-08-28⁩⁦+74⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saAchieved1Approved
Final handoverMS-G5Payment⁦2026-09-30⁩⁦2026-12-24⁩⁦+85⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saLate0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦95%⁩

Awaiting acceptance

⁦5%⁩

Not handed in

⁦0%⁩

Deliverable flow

Pick a stage to filter the register
⁦11⁩ results
Export CSV
Project plan & baseline017-D1⁦4%⁩CRT-017-01ApprovedDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saMunirah A. Al-Khalidi⁦2025-04-14⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting017-D2⁦4%⁩CRT-017-02ApprovedMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saMunirah A. Al-Khalidi⁦2025-06-07⁩V1⁦3⁩ of ⁦3⁩
Business requirements017-D3⁦9%⁩CRT-017-03ApprovedMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saMunirah A. Al-Khalidi⁦2025-07-30⁩V1⁦3⁩ of ⁦3⁩
Solution design017-D4⁦9%⁩CRT-017-04ApprovedSarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.saMunirah A. Al-Khalidi⁦2025-09-21⁩V1⁦3⁩ of ⁦3⁩
Release 1017-D5⁦13%⁩CRT-017-05ApprovedSarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.saMunirah A. Al-Khalidi⁦2025-11-14⁩V1⁦3⁩ of ⁦3⁩
Release 2017-D6⁦14%⁩CRT-017-06ApprovedDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saMunirah A. Al-Khalidi⁦2026-01-06⁩V1⁦3⁩ of ⁦3⁩
Integrations017-D7⁦14%⁩CRT-017-07ApprovedMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saMunirah A. Al-Khalidi⁦2026-03-01⁩V1⁦3⁩ of ⁦3⁩
System testing017-D8⁦10%⁩CRT-017-08ApprovedDana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.saMunirah A. Al-Khalidi⁦2026-04-23⁩V1⁦3⁩ of ⁦3⁩
User acceptance testing017-D9⁦10%⁩CRT-017-09ApprovedMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saMunirah A. Al-Khalidi⁦2026-06-15⁩V1⁦3⁩ of ⁦3⁩
Training & change017-D10⁦8%⁩CRT-017-10ApprovedMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.saMunirah A. Al-Khalidi⁦2026-08-08⁩V1⁦3⁩ of ⁦3⁩
Go-live & handover017-D11⁦5%⁩—SubmittedSarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.saMunirah A. Al-Khalidi⁦2026-09-30⁩V1⁦1⁩ of ⁦3⁩
Total · 11⁦100%⁩
⁦1⁩–⁦11⁩ of ⁦11⁩