Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-018At risk4ExecutionConstructionIn progress

Unified Enterprise Network for HQ & the Branches

Add to watchlist

Fibre and backup links to 14 sites: headquarters, the branches, the service points and the training complex.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 6.6M

Actual cost

SAR 3.7M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 6.8M

SAR +204K

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work6.4M⁦17⁩ elements
Unallocated contingency198KSAR 330K
Budget at completion6.6MPRJ-2026-018
Weighted progress⁦55%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project659⁦2025-05-11⁩⁦2027-03-01⁩⁦55%⁩6.403.74—
1
Phase211⁦2025-05-11⁩⁦2025-12-08⁩⁦100%⁩0.380.41—
1.1
WBS element130⁦2025-05-11⁩⁦2025-09-18⁩⁦100%⁩0.190.200 / 1
1.2
WBS element130⁦2025-07-31⁩⁦2025-12-08⁩⁦100%⁩0.190.201 / 2
2
Phase211⁦2025-10-20⁩⁦2026-05-19⁩⁦100%⁩0.770.82—
2.1
WBS element130⁦2025-10-20⁩⁦2026-02-27⁩⁦100%⁩0.380.411 / 1
2.2
WBS element130⁦2026-01-09⁩⁦2026-05-19⁩⁦100%⁩0.380.411 / 2
3
Phase249⁦2026-03-07⁩⁦2026-11-11⁩⁦97%⁩2.432.52—
3.1
WBS element130⁦2026-03-31⁩⁦2026-08-08⁩⁦100%⁩0.810.861 / 1
3.2
WBS element128⁦2026-06-20⁩⁦2026-10-26⁩⁦100%⁩0.810.861 / 1
3.3
WBS element249⁦2026-03-07⁩⁦2026-11-11⁩⁦92%⁩0.810.791 / 2
4
Phase80⁦2026-10-28⁩⁦2027-01-16⁩⁦0%⁩1.92——
4.1
WBS element36⁦2026-10-28⁩⁦2026-12-03⁩⁦0%⁩0.64—1 / 1
4.2
WBS element36⁦2026-11-19⁩⁦2026-12-25⁩⁦0%⁩0.64—1 / 1
4.3
WBS element36⁦2026-12-11⁩⁦2027-01-16⁩⁦0%⁩0.64—1 / 2
5
Phase58⁦2027-01-02⁩⁦2027-03-01⁩⁦0%⁩0.90——
5.1
WBS element36⁦2027-01-02⁩⁦2027-02-07⁩⁦0%⁩0.45—1 / 1
5.2
WBS element36⁦2027-01-24⁩⁦2027-03-01⁩⁦0%⁩0.45—1 / 1
Total⁦55%⁩6.403.74
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close