PRJ-2026-033On hold3PlanningConstructionStopped

Wadi Al-Dawasir Branch Building

Add to watchlist

On hold pending land allocation and the title deed from the owning entity.

Budget (BAC)

SAR 10.5M

Actual cost

SAR 210K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 10.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
RC-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2025-09-27⁩
Hijri
5 Rabiʻ II 1447 AH
ApprovedPRJ-2026-033Wadi Al-Dawasir Branch Building

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-033
Project
Wadi Al-Dawasir Branch Building
Portfolio
Branches, Service & Training Centres Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Eng. Sami A. Al-Fraih
Project manager
Eng. Shahad M. Al-Malki

1The resultAuto-filled

Priority score

61 of 100

Class

P2

60–74

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the chamber’s strategy⁦20%⁩4.517.5
Value added to the business community⁦12%⁩4.39.9
Financial return & sustainability⁦8%⁩3.95.8
Urgency⁦10%⁩3.46.0
Regulatory requirement⁦10%⁩1.61.5
Risk⁦7%⁩2.74.0
Complexity⁦6%⁩3.03.0
Resource requirement⁦5%⁩3.22.2
Impact on members & beneficiaries⁦14%⁩3.38.0
Sustainability impact⁦3%⁩2.00.8
Digital transformation impact⁦5%⁩2.51.9
Total⁦100%⁩—61

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleSubmitted—⁦2025-09-27⁩ 09:54
2Evaluation checked against the modelMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-09-28⁩ 13:58
3Portfolio manager reviewTechnical acceptanceEng. Abdulrahman S. Al-HarbiPortfolio managerApproved—⁦2025-09-30⁩ 14:05
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-10-02⁩ 09:12

Signatures

Evaluation checked against the model

Ghada A. Al-Shahrani

Approved⁦2025-09-28⁩

Portfolio manager review

Eng. Abdulrahman S. Al-Harbi

Approved⁦2025-09-30⁩

Class approved — Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-10-02⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2025-09-27⁩

  1. Methodology review

    Evaluation checked against the model

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-09-28⁩ at ⁦13:58⁩

  2. Technical acceptance

    Portfolio manager review

    Eng. Abdulrahman S. Al-Harbi · Portfolio manager

    Approved · ⁦2025-09-30⁩ at ⁦14:05⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-10-02⁩ at ⁦09:12⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2025-09-27⁩

    Evaluated on the approved priority model

    Ghada A. Al-Shahrani

Only one version so far.