PRJ-2026-036On track5ClosureConstructionIn progress

Business Centre (Exit 6) Branch Rehabilitation

Add to watchlist

Branch rehabilitation in handover (snags on the fire and alarm systems).

Budget (BAC)

SAR 3.4M

Actual cost

SAR 3.2M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 3.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-03-10⁩
Hijri
29 Shaʻban 1445 AH
ApprovedDMD-2026-036Business Centre (Exit 6) Branch Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Business Centre (Exit 6) Branch Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Waleed O. Al-Juhani

1The proposalAuto-filled

TitleAuto-filled
Business Centre (Exit 6) Branch Rehabilitation
Proposed byAuto-filled
Eng. Waleed O. Al-Juhani
DepartmentAuto-filled
Branches & Service Points Department
Submitted onAuto-filled
⁦2024-03-10⁩
Proposal numberAuto-filled
DMD-2026-036

2Justification

Branch rehabilitation in handover (snags on the fire and alarm systems).

3Objectives

  1. The chamber’s services across Riyadh city and its governorates

Strategic objectives served

  • SO-2.3 — The chamber’s services across Riyadh city and its governorates

4Expected benefits

KindBenefit
ProductivityBranch capacity after rehabilitation — target 4800 visitors / year

5Cost & feasibility

Estimated cost

SAR 3.4M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 2.4M
Supervision & consultingSAR 470K
Internal teamSAR 300K
Contingency reserve (5%)SAR 170K
TotalSAR 3.4M

6Initial risks

RiskLevelProposed response
Preliminary-handover snags on the fire and alarm systemsLowTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2024-03-10⁩ 11:50
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2024-03-11⁩ 09:30
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-03-13⁩ 10:37
4Portfolio manager reviewTechnical acceptanceEng. Mishari K. Al-OtaibiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-03-18⁩ 11:44
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-03-21⁩ 11:26
6Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2024-03-27⁩ 08:00
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-03-28⁩ 13:58

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2024-03-11⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2024-03-13⁩

Portfolio manager review

Eng. Mishari K. Al-Otaibi

Approved⁦2024-03-18⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2024-03-21⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-03-28⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2024-03-10⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2024-03-11⁩ at ⁦09:30⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-03-13⁩ at ⁦10:37⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Mishari K. Al-Otaibi · Portfolio manager

    Approved · ⁦2024-03-18⁩ at ⁦11:44⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-03-21⁩ at ⁦11:26⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-03-28⁩ at ⁦13:58⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-03-31⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Waleed O. Al-Juhani

  2. V1Returned for edit⁦2024-03-10⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Waleed O. Al-Juhani

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close