PRJ-2026-036On track5ClosureConstructionIn progress
Business Centre (Exit 6) Branch Rehabilitation
Add to watchlistBranch rehabilitation in handover (snags on the fire and alarm systems).
Project managerEng. Waleed O. Al-JuhaniProject sponsorSarah A. Al-QarniProgrammeBuilding Rehabilitation & Efficiency Programme
Budget (BAC)
SAR 3.4M
Actual cost
SAR 3.2M
96% of budget
Progress
97%Awaiting acceptance 3%
Estimate at completion
SAR 3.3M
SPI · CPI
0.98Schedule performance index · 0.981.01Cost performance index · 1.01
Forecast finish
2026-11-12
12 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work3.2M17 elements
Unallocated contingency100.5KSAR 168K
Budget at completion3.4MPRJ-2026-036
Weighted progress97%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total97%3.253.22