PRJ-2026-036On track5ClosureConstructionIn progress

Business Centre (Exit 6) Branch Rehabilitation

Add to watchlist

Branch rehabilitation in handover (snags on the fire and alarm systems).

Budget (BAC)

SAR 3.4M

Actual cost

SAR 3.2M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 3.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work3.2M⁦17⁩ elements
Unallocated contingency100.5KSAR 168K
Budget at completion3.4MPRJ-2026-036
Weighted progress⁦97%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project793⁦2024-10-06⁩⁦2026-12-08⁩⁦97%⁩3.253.22—
1
Phase169⁦2024-10-06⁩⁦2025-03-24⁩⁦100%⁩0.190.20—
1.1
WBS element104⁦2024-10-06⁩⁦2025-01-18⁩⁦100%⁩0.100.100 / 1
1.2
WBS element104⁦2024-12-10⁩⁦2025-03-24⁩⁦100%⁩0.100.101 / 2
2
Phase168⁦2025-02-13⁩⁦2025-07-31⁩⁦100%⁩0.390.40—
2.1
WBS element103⁦2025-02-13⁩⁦2025-05-27⁩⁦100%⁩0.190.201 / 1
2.2
WBS element103⁦2025-04-19⁩⁦2025-07-31⁩⁦100%⁩0.190.201 / 2
3
Phase234⁦2025-06-22⁩⁦2026-02-11⁩⁦100%⁩1.231.26—
3.1
WBS element104⁦2025-06-22⁩⁦2025-10-04⁩⁦100%⁩0.410.421 / 1
3.2
WBS element104⁦2025-08-26⁩⁦2025-12-08⁩⁦100%⁩0.410.421 / 1
3.3
WBS element104⁦2025-10-30⁩⁦2026-02-11⁩⁦100%⁩0.410.421 / 2
4
Phase233⁦2026-01-03⁩⁦2026-08-24⁩⁦100%⁩0.971.00—
4.1
WBS element104⁦2026-01-03⁩⁦2026-04-17⁩⁦100%⁩0.320.331 / 1
4.2
WBS element103⁦2026-03-09⁩⁦2026-06-20⁩⁦100%⁩0.320.331 / 1
4.3
WBS element103⁦2026-05-13⁩⁦2026-08-24⁩⁦100%⁩0.320.331 / 2
5
Phase145⁦2026-07-16⁩⁦2026-12-08⁩⁦79%⁩0.450.36—
5.1
WBS element102⁦2026-07-16⁩⁦2026-10-26⁩⁦100%⁩0.230.231 / 1
5.2
WBS element134⁦2026-07-27⁩⁦2026-12-08⁩⁦57%⁩0.230.131 / 1
Total⁦97%⁩3.253.22