Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 92.5K — if approved the value becomes SAR 2.6M
Total
Increase
Decrease
Original valueVO 1Current value
Where the money is now
66% of the current value paid
66%
Paid
1.7M
of a current value of SAR 2.6M
Retention held(10% of each certificate)
168.3K
Advance not yet recovered(of an advance of SAR 243K)
74.7K
Value remaining
867K
AI insight
The contract is heading past its end date
Go-live runs 42 days behind plan. The extension claim was assessed at 28 days and the pending variation (SAR 92.5K) adds 21 days; approving both moves the contract end beyond 31 March 2027.