PRJ-2026-001Off track4ExecutionHybridStalled

Chamber ERP on Dynamics 365

Remove from watchlist

One system on Dynamics 365 for the chamber’s finance, procurement and HR, connected to the My Business portal to collect membership and service fees.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.7M

SAR +440K

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
RC-PMO-F09
Template edition
3.1
Version
V1
Form date
⁦2026-10-09⁩
Hijri
28 Rabiʻ II 1448 AH
In approvalCR-2026-008Increase the customisation & integration budget

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-001
Project
Chamber ERP on Dynamics 365
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The change

TitleAuto-filled
Increase the customisation & integration budget
KindAuto-filled
Budget
Requested byAuto-filled
Dana S. Al-Saleh
Raised onAuto-filled
⁦2026-10-09⁩

Reason

Customisations and the My Business / SADAD integration missed in the tender book

Justification

Without them the financial module cannot go live and membership and attestation fees stay reconciled by hand

2Impact analysis

Cost

SAR +340K

Schedule

+45 days

Risk

16 → 9

Benefits

+3%

Risk impact

Covers the contingency overrun

Benefits impact

Month-end close in 5 days instead of 12

3The approval decision

The PMO’s recommendation

The PMO recommends approval after the independent estimate review

Change Committee decision
Not taken yet
Decided on
—
Decision number
—

Conditions

  • The independent estimate review before signature

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2026-10-09⁩ 11:08
2Project managerTechnical acceptanceDana S. Al-SalehProject managerApproved—⁦2026-10-11⁩ 13:52
3PMO review & impact analysisMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-10-13⁩ 14:59
4Financial impactFinancial approvalApproval engineFinancePre-breach alert—⁦2026-10-15⁩ 08:00

Signatures

Project manager

Dana S. Al-Saleh

Approved⁦2026-10-11⁩

PMO review & impact analysis

Ghada A. Al-Shahrani

Approved⁦2026-10-13⁩

Financial impact

Munirah A. Al-Khalidi

Awaiting decision

Change Committee

Dr. Mohammed I. Al-Subaie

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F09 · version V1

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Dana S. Al-Saleh on ⁦2026-10-09⁩

  1. Technical acceptance

    Project manager

    Dana S. Al-Saleh · Project manager

    Approved · ⁦2026-10-11⁩ at ⁦13:52⁩

  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-10-13⁩ at ⁦14:59⁩

  3. Financial approval

    Financial impact

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    9 working days overdueAction time limit exceeded · Limit 2 working daysLimit 2 working days · Due ⁦2026-10-15⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-15⁩

    Waiting on Khalid N. Al-Mutairi
  4. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Delegated to Dr. Noura M. Al-Otaibi

    Limit 3 working days · Expected by ⁦2026-10-20⁩

Steps that do not apply to this record

  • Contractual impact — the condition «Contract link?» does not hold
  • Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-09⁩

    The request as raised

    Dana S. Al-Saleh

Only one version so far.