Chamber ERP on Dynamics 365
Remove from watchlistOne system on Dynamics 365 for the chamber’s finance, procurement and HR, connected to the My Business portal to collect membership and service fees.
Budget (BAC)
Actual cost
69% of budget
Progress
Estimate at completion
SAR +440K
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure4 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-06-22 | 2025-09-26 | +96 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-24 | 2026-04-12 | +170 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-04-27 | 2026-11-27 | +214 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-08-29 | 2027-01-12 | +136 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-02-27 | +58 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
61%Awaiting acceptance
11%Not handed in
28%Deliverable flow
Display options
| Project plan & baseline001-D1 | 5% | CRT-001-01 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Munirah A. Al-Khalidi | 2025-04-21 | V1 | 3 of 3 |
| Monitoring & reporting001-D2 | 4% | CRT-001-02 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.sa | Munirah A. Al-Khalidi | 2025-06-22 | V1 | 3 of 3 |
| Business requirements001-D3 | 10% | CRT-001-03 | Approved | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.sa | Munirah A. Al-Khalidi | 2025-08-23 | V1 | 3 of 3 |
| Solution design001-D4 | 10% | CRT-001-04 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Munirah A. Al-Khalidi | 2025-10-24 | V1 | 3 of 3 |
| Release 1001-D5 | 16% | CRT-001-05 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Munirah A. Al-Khalidi | 2025-12-25 | V1 | 3 of 3 |
| Release 2001-D6 | 16% | CRT-001-06 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Munirah A. Al-Khalidi | 2026-02-25 | V1 | 3 of 3 |
| Integrations001-D7 | 11% | — | Under review | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.sa | Munirah A. Al-Khalidi | 2026-04-27 | V1 | 1 of 3 |
| System testing001-D8 | 8% | — | Draft | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Munirah A. Al-Khalidi | 2026-06-28 | V0 | 0 of 3 |
| User acceptance testing001-D9 | 8% | — | Draft | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.sa | Munirah A. Al-Khalidi | 2026-08-29 | V0 | 0 of 3 |
| Training & change001-D10 | 6% | — | Draft | Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@chamber.sa | Munirah A. Al-Khalidi | 2026-10-30 | V0 | 0 of 3 |
| Go-live & handover001-D11 | 6% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Munirah A. Al-Khalidi | 2026-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |