PRJ-2026-001Off track4ExecutionHybridStalled

Chamber ERP on Dynamics 365

Remove from watchlist

One system on Dynamics 365 for the chamber’s finance, procurement and HR, connected to the My Business portal to collect membership and service fees.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.7M

SAR +440K

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+58⁩ days vs approved

Baseline (original = approved)⁦2026-12-31⁩
Current forecast⁦2027-02-27⁩
By earned schedule⁦2028-03-04⁩
Critical activities
6
of ⁦8⁩ open activities
Late activities
5
past their baseline finish
Schedule performance
0.62
earned ÷ planned value
Next milestone
in 30 days
Build complete
Expand allCollapse all
Activity
Chamber ERP on Dynamics 365Planned: ⁦2025-01-12⁩ → ⁦2026-12-31⁩Forecast: ⁦2025-01-12⁩ → ⁦2027-02-27⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-01-12⁩ → ⁦2025-06-22⁩Actual: ⁦2025-01-12⁩ → ⁦2025-09-26⁩
Project plan & baselinePlanned: ⁦2025-01-12⁩ → ⁦2025-04-21⁩Actual: ⁦2025-01-12⁩ → ⁦2025-06-19⁩
Monitoring & reportingPlanned: ⁦2025-03-15⁩ → ⁦2025-06-22⁩Actual: ⁦2025-04-21⁩ → ⁦2025-09-26⁩
Project plan approvedPlanned: ⁦2025-06-22⁩ → ⁦2025-06-22⁩Actual: ⁦2025-09-26⁩ → ⁦2025-09-26⁩Project plan approved
Analysis & designPlanned: ⁦2025-05-16⁩ → ⁦2025-10-24⁩Actual: ⁦2025-07-29⁩ → ⁦2026-04-12⁩
Business requirementsPlanned: ⁦2025-05-16⁩ → ⁦2025-08-23⁩Actual: ⁦2025-07-29⁩ → ⁦2026-01-03⁩
Solution designPlanned: ⁦2025-07-17⁩ → ⁦2025-10-24⁩Actual: ⁦2025-11-05⁩ → ⁦2026-04-12⁩
Designs approvedPlanned: ⁦2025-10-24⁩ → ⁦2025-10-24⁩Actual: ⁦2026-04-12⁩ → ⁦2026-04-12⁩Designs approved
BuildPlanned: ⁦2025-09-17⁩ → ⁦2026-04-27⁩Forecast: ⁦2026-01-18⁩ → ⁦2026-11-27⁩Float: ⁦0⁩d
Release 1Planned: ⁦2025-09-17⁩ → ⁦2025-12-25⁩Actual: ⁦2026-02-12⁩ → ⁦2026-07-20⁩
Release 2Planned: ⁦2025-11-17⁩ → ⁦2026-02-25⁩Actual: ⁦2026-05-22⁩ → ⁦2026-10-27⁩
IntegrationsPlanned: ⁦2026-01-18⁩ → ⁦2026-04-27⁩Forecast: ⁦2026-01-18⁩ → ⁦2026-11-27⁩Float: ⁦0⁩dDrag to change its duration+214
Build completePlanned: ⁦2026-04-27⁩ → ⁦2026-04-27⁩Forecast: ⁦2026-11-27⁩ → ⁦2026-11-27⁩Float: ⁦92⁩dDrag to change its datesBuild complete
Testing & acceptancePlanned: ⁦2026-03-21⁩ → ⁦2026-08-29⁩Forecast: ⁦2026-11-13⁩ → ⁦2027-01-12⁩Float: ⁦0⁩d
System testingPlanned: ⁦2026-03-21⁩ → ⁦2026-06-28⁩Forecast: ⁦2026-11-13⁩ → ⁦2026-12-20⁩Float: ⁦0⁩dDrag to change its dates+175
User acceptance testingPlanned: ⁦2026-05-22⁩ → ⁦2026-08-29⁩Forecast: ⁦2026-12-06⁩ → ⁦2027-01-12⁩Float: ⁦0⁩dDrag to change its dates+136
Testing & acceptance completePlanned: ⁦2026-08-29⁩ → ⁦2026-08-29⁩Forecast: ⁦2027-01-12⁩ → ⁦2027-01-12⁩Float: ⁦46⁩dDrag to change its datesTesting & acceptance complete
Launch & handoverPlanned: ⁦2026-07-23⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-29⁩ → ⁦2027-02-27⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-07-23⁩ → ⁦2026-10-30⁩Forecast: ⁦2026-12-29⁩ → ⁦2027-02-04⁩Float: ⁦0⁩dDrag to change its dates+97
Go-live & handoverPlanned: ⁦2026-09-23⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-21⁩ → ⁦2027-02-27⁩Float: ⁦0⁩dDrag to change its dates+58
Final handoverPlanned: ⁦2026-12-31⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-02-27⁩ → ⁦2027-02-27⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦8⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦5⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Integrations” needs a pace ⁦4.0⁩× faster than it has kept

It earned ⁦70%⁩ in 283 days; the forecast assumes the rest in 30 days. At the pace so far it finishes on ⁦2027-02-26⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 135 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

96
170
214
136
58
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Esc