Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-004Critical4ExecutionConstructionStalled

Converting the Current Headquarters into a Member Services Centre & Committee Rooms

Remove from watchlist

Rebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings, and a modern members’ service hall.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 20.6M

Actual cost

SAR 16.7M

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 24.5M

SAR +3.9M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-03-05⁩
Hijri
16 Ramadan 1447 AH
ApprovedCRT-004-06Structure

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-004
Project
Converting the Current Headquarters into a Member Services Centre & Committee Rooms
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Support Services Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Waleed O. Al-Juhani

1The deliverableAuto-filled

DeliverableAuto-filled
Structure
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Waleed O. Al-Juhani
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦13%⁩
DueAuto-filled
⁦2025-06-16⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-004_3.2_v1.pdfV1Eng. Waleed O. Al-Juhani⁦2025-08-28⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Bandar M. Al-Shammari
Accepted byAuto-filled
Sarah A. Al-Qarni
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2024-003
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2025-08-28⁩ 13:46
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-08-31⁩ 13:10
3Inspection & technical acceptance — ownerTechnical acceptanceSarah A. Al-QarniProject ownerOn behalf of Eng. Bandar M. Al-ShammariApprovedInspected and accepted against the approved acceptance criteria.⁦2025-09-03⁩ 14:17
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-09-07⁩ 12:45
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-09-08⁩ 13:22

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-08-31⁩

Inspection & technical acceptance — owner

Sarah A. Al-Qarni

Approved⁦2025-09-03⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-09-07⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-09-08⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2025-08-28⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-08-31⁩ at ⁦13:10⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2025-09-03⁩ at ⁦14:17⁩ · On behalf of Eng. Bandar M. Al-Shammari (Sarah A. Al-Qarni)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-09-07⁩ at ⁦12:45⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-08⁩ at ⁦13:22⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-08-28⁩

    PRJ-2026-004_3.2_v1.pdf

    Eng. Waleed O. Al-Juhani

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close