PRJ-2026-004Critical4ExecutionConstructionStalled

Converting the Current Headquarters into a Member Services Centre & Committee Rooms

Remove from watchlist

Rebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings, and a modern members’ service hall.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 20.6M

Actual cost

SAR 16.7M

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 24.5M

SAR +3.9M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work20M⁦17⁩ elements
Unallocated contingency618KSAR 1M
Budget at completion20.6MPRJ-2026-004
Weighted progress⁦68%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project1,149⁦2024-01-14⁩⁦2027-03-08⁩⁦68%⁩19.9816.68—
1
Phase308⁦2024-01-14⁩⁦2024-11-17⁩⁦100%⁩1.201.47—
1.1
WBS element189⁦2024-01-14⁩⁦2024-07-21⁩⁦100%⁩0.600.740 / 1
1.2
WBS element190⁦2024-05-11⁩⁦2024-11-17⁩⁦100%⁩0.600.741 / 2
2
Phase307⁦2024-09-07⁩⁦2025-07-11⁩⁦100%⁩2.402.94—
2.1
WBS element189⁦2024-09-07⁩⁦2025-03-15⁩⁦100%⁩1.201.471 / 1
2.2
WBS element189⁦2025-01-03⁩⁦2025-07-11⁩⁦100%⁩1.201.471 / 2
3
Phase426⁦2025-05-01⁩⁦2026-07-01⁩⁦100%⁩7.599.32—
3.1
WBS element190⁦2025-05-01⁩⁦2025-11-07⁩⁦100%⁩2.533.111 / 1
3.2
WBS element189⁦2025-08-28⁩⁦2026-03-05⁩⁦100%⁩2.533.111 / 1
3.3
WBS element189⁦2025-12-24⁩⁦2026-07-01⁩⁦100%⁩2.533.111 / 2
4
Phase500⁦2025-10-04⁩⁦2027-02-16⁩⁦40%⁩5.992.94—
4.1
WBS element188⁦2026-04-21⁩⁦2026-10-26⁩⁦100%⁩2.002.451 / 1
4.2
WBS element490⁦2025-10-04⁩⁦2027-02-06⁩⁦20%⁩2.000.491 / 1
4.3
WBS element16⁦2027-01-31⁩⁦2027-02-16⁩⁦0%⁩2.00—1 / 2
5
Phase26⁦2027-02-10⁩⁦2027-03-08⁩⁦0%⁩2.80——
5.1
WBS element16⁦2027-02-10⁩⁦2027-02-26⁩⁦0%⁩1.40—1 / 1
5.2
WBS element16⁦2027-02-20⁩⁦2027-03-08⁩⁦0%⁩1.40—1 / 1
Total⁦68%⁩19.9816.68