Member 360 — Member Relationship Management on Dynamics 365
Add to watchlistOne record for every member business — its membership, transactions, enquiries, events and committees — linked to the Ministry of Commerce commercial register and the Saudi Business Center.
Budget (BAC)
Actual cost
6% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution30 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-11-04 | 2026-12-04 | +30 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-02-05 | 2027-03-02 | +25 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-06-26 | 2027-07-12 | +16 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | On track | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-09-27 | 2027-10-08 | +11 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | On track | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-12-30 | 2028-01-04 | +5 days | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
6%Awaiting acceptance
4%Not handed in
90%Deliverable flow
Display options
| Project plan & baseline011-D1 | 6% | CRT-011-01 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Badr N. Al-Haqbani | 2026-09-18 | V1 | 3 of 3 |
| Monitoring & reporting011-D2 | 4% | — | Submitted | Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa | Badr N. Al-Haqbani | 2026-11-04 | V1 | 1 of 3 |
| Business requirements011-D3 | 8% | — | Draft | Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa | Badr N. Al-Haqbani | 2026-12-21 | V0 | 0 of 3 |
| Solution design011-D4 | 8% | — | Draft | Eng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.sa | Badr N. Al-Haqbani | 2027-02-05 | V0 | 0 of 3 |
| Release 1011-D5 | 13% | — | Draft | Eng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.sa | Badr N. Al-Haqbani | 2027-03-24 | V0 | 0 of 3 |
| Release 2011-D6 | 13% | — | Draft | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Badr N. Al-Haqbani | 2027-05-10 | V0 | 0 of 3 |
| Integrations011-D7 | 13% | — | Draft | Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa | Badr N. Al-Haqbani | 2027-06-26 | V0 | 0 of 3 |
| System testing011-D8 | 10% | — | Draft | Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@chamber.sa | Badr N. Al-Haqbani | 2027-08-12 | V0 | 0 of 3 |
| User acceptance testing011-D9 | 10% | — | Draft | Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa | Badr N. Al-Haqbani | 2027-09-27 | V0 | 0 of 3 |
| Training & change011-D10 | 8% | — | Draft | Badr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.sa | Badr N. Al-Haqbani | 2027-11-13 | V0 | 0 of 3 |
| Go-live & handover011-D11 | 7% | — | Draft | Eng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.sa | Badr N. Al-Haqbani | 2027-12-30 | V0 | 0 of 3 |
| Total · 11 | 100% |