My Business Portal 2.0 — the Unified Member Journey
Remove from watchlist
68 member e-services in one journey — membership and renewal, e-attestation, certificates of origin, document verification and appointments — with Nafath sign-in and links to the Ministry of Commerce and the Saudi Business Center.
Early warning: 74% chance of slipping within 45 days
Budget (BAC)
SAR 4.3M
Actual cost
SAR 2.6M
60% of budget
Progress
58%Awaiting acceptance 23%
Estimate at completion
SAR 4.5M
SAR +180K
SPI · CPI
0.87Schedule performance index · 0.870.96Cost performance index · 0.96
Forecast finish
2027-05-12
42 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure31 March 2027
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+42 days vs approved
Original baseline2027-03-13
Approved baseline2027-03-31
Current forecast2027-05-12
By earned schedule2027-06-27
Critical activities
14
of 34 open activities
Late activities
27
past their baseline finish
Schedule performance
0.87
earned ÷ planned value
Next milestone
in 15 days
Wave 1 development complete (24 services)
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2025
2026
2027
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Today
2027-05-1258%
My Business Portal 2.0Planned: 2025-01-05 → 2027-03-31Forecast: 2025-01-05 → 2027-05-12Float: 0d
Government Service Bus integrationPlanned: 2026-05-01 → 2026-10-31Forecast: 2026-05-20 → 2026-12-10Float: 0d
2027-01-3127%
Chamber internal systems integration (Dynamics 365)Planned: 2026-06-01 → 2026-12-31Forecast: 2026-06-15 → 2027-01-31Float: 101dDrag to change its duration+31
2026-12-100%
Nafath & Government Service Bus integration completePlanned: 2026-10-31 → 2026-10-31Forecast: 2026-12-10 → 2026-12-10Float: 0dDrag to change its datesNafath & Government Service Bus integration complete
2027-02-1045%
Data migrationPlanned: 2026-04-01 → 2026-12-31Forecast: 2026-04-01 → 2027-02-10Float: 91d
2026-11-3070%
Member & company data profiling & cleansingPlanned: 2026-04-01 → 2026-10-31Forecast: 2026-04-01 → 2026-11-30Float: 113dDrag to change its duration+30
2026-07-14100%
Data classification approved by the data officePlanned: 2026-06-30 → 2026-06-30Actual: 2026-07-14 → 2026-07-14Data classification approved by the data office
2027-02-1020%
Membership records migration & reconciliationPlanned: 2026-09-01 → 2026-12-31Forecast: 2026-09-20 → 2027-02-10Float: 91dDrag to change its duration+41