PRJ-2026-014At risk4ExecutionHybridIn progress

My Business Portal 2.0 — the Unified Member Journey

Remove from watchlist

68 member e-services in one journey — membership and renewal, e-attestation, certificates of origin, document verification and appointments — with Nafath sign-in and links to the Ministry of Commerce and the Saudi Business Center.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 4.3M

Actual cost

SAR 2.6M

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SAR 4.5M

SAR +180K

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

⁦The project delivers My Business Portal 2⁩.⁦0⁩: ⁦68 e-services for member businesses⁩ — membership and renewal, e-attestation, certificates of origin, document verification, appointment booking and the membership fee calculator — in a single member journey, with Nafath sign-in, commercial-register data from the Ministry of Commerce through the Government Service Bus and fees through SADAD, and a no-code request workflow and forms engine; ⁦membership records and business data are migrated and 420 chamber and branch staff trained⁩, ⁦within SAR 4⁩.⁦32M and an official launch targeted for March 2027⁩.

In scope

  • A unified My Business portal in the Riyadh Chamber identity, meeting accessibility standards, with the membership-fee calculator
  • Single sign-on through Nafath; commercial-register data and SADAD fee payment through the Government Service Bus
  • A configurable, no-code request workflow and forms engine
  • Migration of memberships, open requests and business records from the current My Business portal
  • ⁦Change management and training for 420 chamber and branch staff⁩

Out of scope

  • The mobile app (⁦separate project PRJ-2026-015⁩)
  • Re-engineering procedures that would need changes to the Chambers of Commerce Law or its bylaws
  • The «⁦Member 360⁩» CRM (⁦separate project PRJ-2026-011⁩)

Acceptance criteria

  • Wave 1 service package⁦24 services pass UAT at 98% with no critical defects⁩
  • Nafath & Government Service Bus interfacesProduction sign-off from Nafath and from the Government Service Bus operator
  • Membership & open-request migration⁦100% record-count match⁩, ⁦99.5% on mandatory fields⁩
  • Portal at launch⁦Under 2 s for 95% of requests⁩; ⁦99.9% availability⁩
  • CybersecurityNo critical/high pen-test findings; ECC compliance certificate

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Superseded⁦2025-02-16⁩

    ⁦First baseline with charter V3⁩

    Budget4.2MFinish⁦2027-03-31⁩
  2. 2

    SB-2Current⁦2026-02-24⁩

    Nafath sign-in for businesses’ signatories and agents added (+SAR ⁦120K⁩, ⁦+18 days absorbed⁩)

    Budget4.3M⁦+2.9%⁩Finish⁦2027-03-31⁩
    CR-2026-001
  3. 3

    SB-3Proposed⁦2026-10-29⁩

    Proposed: membership transfer & record merge (⁦+SAR 92⁩.⁦5K⁩, ⁦+21 days⁩)

    Budget4.4M⁦+5.1%⁩Finish⁦2027-04-21⁩
    CR-2026-004

Requirements registerRequired at this stage

⁦25⁩ requirements of five kinds, with the trace status of each

By type

  • Business4
  • Functional7
  • Technical6
  • Regulatory4
  • Security4

Fully traced

⁦92%⁩

23/25 · linked to a deliverable, task and test

Test passed

⁦28%⁩

7/25 · test result is a pass

Accepted

⁦28%⁩

7/25 · signed off by the business owner

⁦25⁩ results
Export CSV
REQ-001One member journey for every e-service from a single business fileBusinessMustApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceP-003f.alshehri@chamber.saSB-1
REQ-002⁦Cut membership and attestation requests that need checking from 21 days to 5⁩BusinessMustApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceP-003f.alshehri@chamber.saSB-1
REQ-003A company file with each request’s status, certificates, membership and notificationsBusinessShouldApprovedLama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Member ServicesP-006l.alharbi@chamber.saSB-1
REQ-004Nafath single sign-on for member business ownersFunctionalMustIn progressHussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@chamber.saSB-1
REQ-005Businesses’ authorised signatories and agents sign in through Nafath, with an authorisation checkFunctionalMustIn progressHussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@chamber.saSB-2
REQ-006Pull commercial-register data from the Ministry of Commerce through the Government Service BusFunctionalMustIn progressHussam T. Al-QurashiHussam T. Al-QurashiSenior Software Engineer – IntegrationP-030h.alqurashi@chamber.saSB-1
REQ-007A request forms engine the business configures without codeFunctionalMustCompletedLama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Member ServicesP-006l.alharbi@chamber.saSB-1
REQ-008Membership issue & renewal workflow with action time limits and auto-escalationFunctionalMustCompletedLama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Member ServicesP-006l.alharbi@chamber.saSB-1
REQ-009Company data refreshed from the commercial register within one working day, source recordedFunctionalShouldIn progressYousef A. Al-OmariYousef A. Al-OmariExecutive Director, Events & Trade DelegationsP-016y.alomari@chamber.saSB-1
REQ-010A chat assistant for members’ frequent questionsFunctionalCouldDeferredLama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Member ServicesP-006l.alharbi@chamber.sa—
⁦1⁩–⁦10⁩ of ⁦25⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. ⁦2⁩ requirements have a gap.