Working
Working baseline
- Finish
- 2028-01-01
- Budget
- SAR 1.4M
- 16 activities
The working plan before the first baseline: a snapshot of it is saved and sent for approval at the planning gate.
Created 2026-10-28 · by Rahaf I. Al-Nefaie
Follow every recommendation from its sectoral committee to the government body concerned until it is decided, with a dashboard for the board and committee members.
Budget (BAC)
Actual cost
1% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
InitiationStage 2 of 5
Next gate:Planning6 September 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
No baseline approved yet
The project is in Initiation: the working plan is ready (16 activities, finish 2028-01-01, budget SAR 1.4M). Save it as the first baseline and send it for approval; once approved it is locked and changes only through an approved change request.
Working
The working plan before the first baseline: a snapshot of it is saved and sent for approval at the planning gate.
Created 2026-10-28 · by Rahaf I. Al-Nefaie
What changed from version A to version B
No approved baseline yet — measured against the working plan
Every saved version with its reason and reference