Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-023On track2InitiationAgileNot started

Sectoral Committee Recommendations Tracker

Add to watchlist

Follow every recommendation from its sectoral committee to the government body concerned until it is decided, with a dashboard for the board and committee members.

Budget (BAC)

SAR 1.4M

Actual cost

SAR 14K

⁦1%⁩ of budget

Progress

⁦1%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 1.4M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationStage ⁦2⁩ of ⁦5⁩

Next gate:Planning6 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current stageInitiation · Current stage
  3. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Closure readiness

Closure planned after the forecast finish on ⁦2027-12-31⁩

A preview of what closure will need, with the planned dates, and the lessons captured so far.

0/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedNot started

    Final acceptance of every deliverable

    Hala F. Al-AngariPlanned ⁦2027-12-21⁩

  2. 2

    Financial closureNot started

    Spend reconciled, commitments closed

    Khalid N. Al-MutairiPlanned ⁦2028-01-20⁩

  3. 3

    Contract closureNot started

    Contracts closed, retention released

    Khalid N. Al-MutairiPlanned ⁦2028-01-30⁩

  4. 4

    Documents archivedNot started

    Documents archived with classification

    Rahaf I. Al-NefaiePlanned ⁦2028-01-25⁩

  5. 5

    Lessons learnedNot started

    Lessons-learned session

    Rahaf I. Al-NefaiePlanned ⁦2028-01-15⁩

  6. 6

    Benefits owner assignedNot started

    Benefits handed to their owner with a measurement plan

    Hala F. Al-AngariPlanned ⁦2028-01-10⁩

  7. 7

    Final report approvedNot started

    Final report and its approval

    Rahaf I. Al-NefaiePlanned ⁦2028-02-04⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

The review comes after closure

About three months after the forecast finish (⁦2027-12-31⁩), with the sponsor and the benefits owner.

Lessons learned

0 lessons — offered automatically to similar projects when they are created.

Knowledge base

No lessons captured yet

Capture what the team learned during delivery; closure needs at least one.

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.

No benefits recorded for this project.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close