Follow every recommendation from its sectoral committee to the government body concerned until it is decided, with a dashboard for the board and committee members.
1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Forecast finish
2027-12-31
On baseline
Initiation·Stage 2 of 5
Next gate:Planning6 September 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current stageInitiation · Current stage
Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Project plan & baselinePlanned: 2026-09-06 → 2026-11-11Forecast: 2026-09-06 → 2026-12-17Float: 0dDrag to change its duration+36
2027-01-240%
Monitoring & reportingPlanned: 2026-10-17 → 2026-12-23Forecast: 2026-11-24 → 2027-01-24Float: 0dDrag to change its dates+32
2027-01-240%
Project plan approvedPlanned: 2026-12-23 → 2026-12-23Forecast: 2027-01-24 → 2027-01-24Float: 342dDrag to change its datesProject plan approved