PRJ-2026-031On track5ClosureScrumCompleted

Certificate of Origin & e-Attestation Automation

Add to watchlist

Completed: certificates of origin, document attestation and verification fully online.

Budget (BAC)

SAR 410K

Actual cost

SAR 398K

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 398K

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2023-09-10⁩
Hijri
25 Safar 1445 AH
ApprovedDMD-2026-031Certificate of Origin & e-Attestation Automation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-031
Project
Certificate of Origin & e-Attestation Automation
Portfolio
Member Services & Business Voice Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Karim Haddad

1The proposalAuto-filled

TitleAuto-filled
Certificate of Origin & e-Attestation Automation
Proposed byAuto-filled
Karim Haddad
DepartmentAuto-filled
Membership & Attestation Department
Submitted onAuto-filled
⁦2023-09-10⁩
Proposal numberAuto-filled
DMD-2026-031

2Justification

Completed: certificates of origin, document attestation and verification fully online.

3Objectives

  1. High-quality, value-adding digital core services for members

Strategic objectives served

  • SO-2.1 — High-quality, value-adding digital core services for members

4Expected benefits

KindBenefit
Time savedShorter time to issue a certificate of origin — target 15 minutes
SatisfactionHigher member satisfaction with e-attestation — target 85 %

5Cost & feasibility

Estimated cost

SAR 410K

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 295K
Supervision & consultingSAR 60K
Internal teamSAR 35K
Contingency reserve (5%)SAR 20K
TotalSAR 410K

6Initial risks

RiskLevelProposed response
No initial risks recorded

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Karim HaddadSenior Digital Delivery Consultant — PMOSubmitted—⁦2023-09-10⁩ 12:15
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2023-09-12⁩ 10:25
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2023-09-17⁩ 11:32
4Portfolio manager reviewTechnical acceptanceFaisal A. Al-ShehriPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2023-09-18⁩ 12:39
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2023-09-20⁩ 12:51
6Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2023-09-26⁩ 08:00
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2023-09-27⁩ 14:53

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2023-09-12⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2023-09-17⁩

Portfolio manager review

Faisal A. Al-Shehri

Approved⁦2023-09-18⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2023-09-20⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2023-09-27⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Karim Haddad on ⁦2023-09-10⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2023-09-12⁩ at ⁦10:25⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2023-09-17⁩ at ⁦11:32⁩

  3. Technical acceptance

    Portfolio manager review

    Faisal A. Al-Shehri · Portfolio manager

    Approved · ⁦2023-09-18⁩ at ⁦12:39⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2023-09-20⁩ at ⁦12:51⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2023-09-27⁩ at ⁦14:53⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2023-10-01⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Karim Haddad

  2. V1Returned for edit⁦2023-09-10⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Karim Haddad

Esc

Quick actions

Go to

Projects