PRJ-2026-031On track5ClosureScrumCompleted

Certificate of Origin & e-Attestation Automation

Add to watchlist

Completed: certificates of origin, document attestation and verification fully online.

Budget (BAC)

SAR 410K

Actual cost

SAR 398K

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 398K

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Project charter

Objective, scope, deliverables, roles and budget

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
RC-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2024-04-05⁩
Hijri
26 Ramadan 1445 AH
ApprovedPRJ-2026-031Certificate of Origin & e-Attestation Automation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-031
Project
Certificate of Origin & e-Attestation Automation
Portfolio
Member Services & Business Voice Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Karim Haddad

1Objective

Background

Completed: certificates of origin, document attestation and verification fully online.

Project objectives

  1. High-quality, value-adding digital core services for members

2Scope

In scope

  • Completed: certificates of origin, document attestation and verification fully online.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2024-04-25⁩
Main deliverable — stage 1⁦2024-11-22⁩
Main deliverable — final stage⁦2025-04-28⁩
Final report⁦2025-06-30⁩
MilestoneDate
Charter approved⁦2024-04-05⁩
Contract signed⁦2024-06-18⁩
50% of works complete⁦2024-11-22⁩
Provisional acceptance⁦2025-05-25⁩
Closure⁦2025-06-30⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Majed S. Al-Rasheed
Project ownerAuto-filled
Badr N. Al-Haqbani
Project managerAuto-filled
Karim Haddad
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 295K
Supervision & consultingSAR 60K
Internal teamSAR 35K
Contingency reserve (5%)SAR 20K
Approved budgetSAR 410K

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Karim HaddadSenior Digital Delivery Consultant — PMOSubmitted—⁦2024-03-27⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2024-03-30⁩ 12:30
3Project ownerTechnical acceptanceBadr N. Al-HaqbaniProject ownerApproved—⁦2024-04-02⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-04-03⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Majed S. Al-RasheedProject sponsorApproved—⁦2024-04-05⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2024-03-30⁩

Project owner

Badr N. Al-Haqbani

Approved⁦2024-04-02⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2024-04-03⁩

Sponsor approval

Eng. Majed S. Al-Rasheed

Approved⁦2024-04-05⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Karim Haddad on ⁦2024-03-27⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2024-03-30⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Badr N. Al-Haqbani · Project owner

    Approved · ⁦2024-04-02⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-04-03⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Majed S. Al-Rasheed · Project sponsor

    Approved · ⁦2024-04-05⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-04-05⁩

    Approved version

    • PMO comments addressed

    Karim Haddad

  2. V1Returned for edit⁦2024-03-17⁩

    First draft

    • Returned to detail the budget

    Karim Haddad