Certificate of Origin & e-Attestation Automation Subtask Last item under this branch 2025-07-20 100% Certificate of Origin & e-Attestation Automation Planned: 2024-04-07 → 2025-06-30 Actual: 2024-04-07 → 2025-07-20
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2024-07-21 100% Management & governance Planned: 2024-04-07 → 2024-07-17 Actual: 2024-04-07 → 2024-07-21
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-06-11 100% Project plan & baseline Planned: 2024-04-07 → 2024-06-08 Actual: 2024-04-07 → 2024-06-11
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-07-21 100% Monitoring & reporting Planned: 2024-05-16 → 2024-07-17 Actual: 2024-05-17 → 2024-07-21
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-07-21 100% Project plan approved Planned: 2024-07-17 → 2024-07-17 Actual: 2024-07-21 → 2024-07-21 Project plan approved
2 Analysis & design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2024-10-10 100% Analysis & design Planned: 2024-06-23 → 2024-10-02 Actual: 2024-06-27 → 2024-10-10
2.1 Business requirements Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-08-31 100% Business requirements Planned: 2024-06-23 → 2024-08-24 Actual: 2024-06-27 → 2024-08-31
2.2 Solution design Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-10-10 100% Solution design Planned: 2024-08-01 → 2024-10-02 Actual: 2024-08-06 → 2024-10-10
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-10-10 100% Designs approved Planned: 2024-10-02 → 2024-10-02 Actual: 2024-10-10 → 2024-10-10 Designs approved
3 Build Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-02-08 100% Build Planned: 2024-09-09 → 2025-01-26 Actual: 2024-09-16 → 2025-02-08
3.1 Release 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-11-19 100% Release 1 Planned: 2024-09-09 → 2024-11-10 Actual: 2024-09-16 → 2024-11-19
3.2 Release 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-12-30 100% Release 2 Planned: 2024-10-18 → 2024-12-18 Actual: 2024-10-26 → 2024-12-30
3.3 Integrations Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-02-08 100% Integrations Planned: 2024-11-25 → 2025-01-26 Actual: 2024-12-06 → 2025-02-08
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-02-08 100% Build complete Planned: 2025-01-26 → 2025-01-26 Actual: 2025-02-08 → 2025-02-08 Build complete
4 Testing & acceptance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-04-30 100% Testing & acceptance Planned: 2025-01-03 → 2025-04-14 Actual: 2025-01-15 → 2025-04-30
4.1 System testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-03-21 100% System testing Planned: 2025-01-03 → 2025-03-06 Actual: 2025-01-15 → 2025-03-21
4.2 User acceptance testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-04-30 100% User acceptance testing Planned: 2025-02-11 → 2025-04-14 Actual: 2025-02-24 → 2025-04-30
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-04-30 100% Testing & acceptance complete Planned: 2025-04-14 → 2025-04-14 Actual: 2025-04-30 → 2025-04-30 Testing & acceptance complete
5 Launch & handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-07-20 100% Launch & handover Planned: 2025-03-21 → 2025-06-30 Actual: 2025-04-06 → 2025-07-20
5.1 Training & change Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-06-10 100% Training & change Planned: 2025-03-21 → 2025-05-22 Actual: 2025-04-06 → 2025-06-10
5.2 Go-live & handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-07-20 100% Go-live & handover Planned: 2025-04-29 → 2025-06-30 Actual: 2025-05-16 → 2025-07-20
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-07-20 100% Final handover Planned: 2025-06-30 → 2025-06-30 Actual: 2025-07-20 → 2025-07-20 Final handover