PRJ-2026-033On hold3PlanningConstructionStopped

Wadi Al-Dawasir Branch Building

Add to watchlist

On hold pending land allocation and the title deed from the owning entity.

Budget (BAC)

SAR 10.5M

Actual cost

SAR 210K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 10.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-08-03⁩
Hijri
9 Safar 1447 AH
ApprovedDMD-2026-033Wadi Al-Dawasir Branch Building

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-033
Project
Wadi Al-Dawasir Branch Building
Portfolio
Branches, Service & Training Centres Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Eng. Sami A. Al-Fraih
Project manager
Eng. Shahad M. Al-Malki

1The proposalAuto-filled

TitleAuto-filled
Wadi Al-Dawasir Branch Building
Proposed byAuto-filled
Eng. Shahad M. Al-Malki
DepartmentAuto-filled
Branches & Service Points Department
Submitted onAuto-filled
⁦2025-08-03⁩
Proposal numberAuto-filled
DMD-2026-033

2Justification

On hold pending land allocation and the title deed from the owning entity.

3Objectives

  1. The chamber’s services across Riyadh city and its governorates

Strategic objectives served

  • SO-2.3 — The chamber’s services across Riyadh city and its governorates

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 10.5M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 7.6M
Supervision & consultingSAR 1.5M
Internal teamSAR 945K
Contingency reserve (5%)SAR 525K
TotalSAR 10.5M

6Initial risks

RiskLevelProposed response
Late land allocation and title deed from the owning entity in Wadi Al-DawasirHighTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesSubmitted—⁦2025-08-03⁩ 14:29
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2025-08-05⁩ 12:39
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-08-07⁩ 13:46
4Portfolio manager reviewTechnical acceptanceEng. Abdulrahman S. Al-HarbiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-08-12⁩ 14:53
5Cost & funding reviewFinancial approvalApproval engineFinancePre-breach alert—⁦2025-08-17⁩ 08:00
6Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-08-18⁩ 14:05
7Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-08-20⁩ 10:07

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2025-08-05⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2025-08-07⁩

Portfolio manager review

Eng. Abdulrahman S. Al-Harbi

Approved⁦2025-08-12⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2025-08-18⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-08-20⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Shahad M. Al-Malki on ⁦2025-08-03⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2025-08-05⁩ at ⁦12:39⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-08-07⁩ at ⁦13:46⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Abdulrahman S. Al-Harbi · Portfolio manager

    Approved · ⁦2025-08-12⁩ at ⁦14:53⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-08-18⁩ at ⁦14:05⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-08-20⁩ at ⁦10:07⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-08-24⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Shahad M. Al-Malki

  2. V1Returned for edit⁦2025-08-03⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Shahad M. Al-Malki

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close