PRJ-2026-001Off track4ExecutionHybridStalled

Chamber ERP on Dynamics 365

Remove from watchlist

One system on Dynamics 365 for the chamber’s finance, procurement and HR, connected to the My Business portal to collect membership and service fees.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.7M

SAR +440K

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work3.1M⁦16⁩ elements
Unallocated contingency96.8KSAR 161K
Budget at completion3.2MPRJ-2026-001
Weighted progress⁦61%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project776⁦2025-01-12⁩⁦2027-02-27⁩⁦61%⁩3.132.24—
1
Phase257⁦2025-01-12⁩⁦2025-09-26⁩⁦100%⁩0.250.29—
1.1
WBS element158⁦2025-01-12⁩⁦2025-06-19⁩⁦100%⁩0.130.150 / 1
1.2
WBS element158⁦2025-04-21⁩⁦2025-09-26⁩⁦100%⁩0.130.151 / 2
2
Phase257⁦2025-07-29⁩⁦2026-04-12⁩⁦100%⁩0.530.62—
2.1
WBS element158⁦2025-07-29⁩⁦2026-01-03⁩⁦100%⁩0.270.311 / 1
2.2
WBS element158⁦2025-11-05⁩⁦2026-04-12⁩⁦100%⁩0.270.311 / 2
3
Phase313⁦2026-01-18⁩⁦2026-11-27⁩⁦90%⁩1.251.32—
3.1
WBS element158⁦2026-02-12⁩⁦2026-07-20⁩⁦100%⁩0.420.491 / 1
3.2
WBS element158⁦2026-05-22⁩⁦2026-10-27⁩⁦100%⁩0.420.491 / 1
3.3
WBS element313⁦2026-01-18⁩⁦2026-11-27⁩⁦70%⁩0.420.341 / 2
4
Phase60⁦2026-11-13⁩⁦2027-01-12⁩⁦0%⁩0.63——
4.1
WBS element37⁦2026-11-13⁩⁦2026-12-20⁩⁦0%⁩0.31—1 / 1
4.2
WBS element37⁦2026-12-06⁩⁦2027-01-12⁩⁦0%⁩0.31—1 / 2
5
Phase60⁦2026-12-29⁩⁦2027-02-27⁩⁦0%⁩0.47——
5.1
WBS element37⁦2026-12-29⁩⁦2027-02-04⁩⁦0%⁩0.23—1 / 1
5.2
WBS element37⁦2027-01-21⁩⁦2027-02-27⁩⁦0%⁩0.23—1 / 1
Total⁦61%⁩3.132.24