PRJ-2026-004Critical4ExecutionConstructionStalled

Converting the Current Headquarters into a Member Services Centre & Committee Rooms

Remove from watchlist

Rebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings, and a modern members’ service hall.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 20.6M

Actual cost

SAR 16.7M

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 24.5M

SAR +3.9M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Converting the Current Headquarters into a Member Services Centre & Committee Rooms

PRJ-2026-004 · Support Services Sector · Operational · WP-2024-004

StalledCritical4ExecutionProject manager: Eng. Waleed O. Al-Juhani · Sponsor: Sarah A. Al-Qarni
Progress
⁦68%⁩ / ⁦92%⁩
SPI · CPI
0.74 · 0.84
Spend
SAR 16.7M / SAR 20.6M
Estimate at completion
SAR 24.5M

Schedule

⁦24%⁩ behind⁦68%⁩

Planned to date ⁦92%⁩

Forecast finish: 2027-02-0326 Shaʻban 1448 AH · 126 days late

SPI0.74Schedule performance index · 0.74CPI0.84Cost performance index · 0.84

Health dimensions

Critical

Last update: 2026-10-2110 Jumada I 1448 AH · Up to date

Deliverables

⁦5⁩ of ⁦12⁩ due deliverables accepted on time (⁦42%⁩)

Next milestones

  • Testing & acceptance complete2027-02-169 Ramadan 1448 AH
  • Final handover2027-03-0829 Ramadan 1448 AH

Top risks

  • Main contractor cash-flow distress and unpaid subcontractors25
  • Fire-fighting and evacuation systems failing Civil Defence requirements15
  • Central HVAC failures during commissioning12

Open impediments

  • Site labour stopped for 4 days over late wages · Escalated
  • Leak in the underground water tanks during the water-tightness test · Open
  • Incomplete bills of quantities attached to certificate 33 · Open

Decisions and changes waiting

  • Direct payment to subcontractors on the current-HQ rehabilitation

Copilot summary

The scope holds 1 project with a budget of SAR 20.6M: 0 on track and 1 red or critical. Weighted progress is 68% against 92% planned, spend SAR 16.7M, and EAC SAR 24.5M (SAR 3.9M over).

1 project is more than a month behind baseline; the worst: Converting the Current Headquarters into a Member Services Centre & Committee Rooms (126 days).

Riyadh Chamber of Commerce & Industry · prepared by Eng. Waleed O. Al-Juhani in MunjazInternal

Status: Critical ·Project page