PRJ-2026-004Critical4ExecutionConstructionStalled

Converting the Current Headquarters into a Member Services Centre & Committee Rooms

Remove from watchlist

Rebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings, and a modern members’ service hall.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 20.6M

Actual cost

SAR 16.7M

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 24.5M

SAR +3.9M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
RC-PMO-F09
Template edition
3.1
Version
V2
Form date
⁦2026-01-18⁩
Hijri
29 Rajab 1447 AH
ApprovedCR-2026-003Add a wing of sectoral committee rooms

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-004
Project
Converting the Current Headquarters into a Member Services Centre & Committee Rooms
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Support Services Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Waleed O. Al-Juhani

1The change

TitleAuto-filled
Add a wing of sectoral committee rooms
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Waleed O. Al-Juhani
Raised onAuto-filled
⁦2026-01-18⁩

Reason

A directive to provide sectoral committee rooms at HQ once the 19th-cycle committees are active

Justification

The existing rooms cannot host the 37 committees’ meetings; without the wing about a third are held off-site

2Impact analysis

Cost

SAR +1.1M

Schedule

+45 days

Risk

20 → 15

Benefits

+22%

Risk impact

The new wing is designed to Civil Defence rules from the start

Benefits impact

28 new committee rooms that host every sectoral committee meeting at HQ

3The approval decision

The PMO’s recommendation

The PMO recommends approval: the change serves the active-committees objective directly

Change Committee decision
Approve
Decided on
⁦2026-02-05⁩
Decision number
DEC-2026-005

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2026-01-18⁩ 12:33
2Project managerTechnical acceptanceEng. Waleed O. Al-JuhaniProject managerApproved—⁦2026-01-19⁩ 14:47
3PMO review & impact analysisMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-01-20⁩ 09:54
4Financial impactFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-01-21⁩ 13:52
5Contractual impactFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-01-25⁩ 14:29
6Change CommitteeTechnical acceptanceDr. Mohammed I. Al-SubaieChange CommitteeApproved—⁦2026-01-26⁩ 12:15
7Projects Steering CommitteeTechnical acceptanceDr. Abdullah S. Al-QahtaniStrategy & Projects Steering CommitteeApproved—⁦2026-01-27⁩ 09:30

Signatures

Project manager

Eng. Waleed O. Al-Juhani

Approved⁦2026-01-19⁩

PMO review & impact analysis

Ghada A. Al-Shahrani

Approved⁦2026-01-20⁩

Financial impact

Munirah A. Al-Khalidi

Approved⁦2026-01-21⁩

Contractual impact

Mazen A. Al-Hazmi

Approved⁦2026-01-25⁩

Change Committee

Dr. Mohammed I. Al-Subaie

Approved⁦2026-01-26⁩

Projects Steering Committee

Dr. Abdullah S. Al-Qahtani

Approved⁦2026-01-27⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F09 · version V2

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2026-01-18⁩

  1. Technical acceptance

    Project manager

    Eng. Waleed O. Al-Juhani · Project manager

    Approved · ⁦2026-01-19⁩ at ⁦14:47⁩

  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-01-20⁩ at ⁦09:54⁩

  3. Financial approval

    Financial impact

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-01-21⁩ at ⁦13:52⁩

  4. Financial approval

    Contractual impact

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-01-25⁩ at ⁦14:29⁩

  5. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Approved · ⁦2026-01-26⁩ at ⁦12:15⁩

  6. Technical acceptance

    Projects Steering Committee

    Dr. Abdullah S. Al-Qahtani · Strategy & Projects Steering Committee

    On the path because: Cost impact above the Change Committee’s authority?From the authority matrix

    Approved · ⁦2026-01-27⁩ at ⁦09:30⁩

Steps that do not apply to this record

  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-02-05⁩

    Approved by the committee

    Eng. Waleed O. Al-Juhani

  2. V1Returned for edit⁦2026-01-18⁩

    The request as raised