Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- RC-PMO-F09
- Template edition
- 3.1
- Version
- V2
- Form date
- 2026-01-18
- Hijri
- 29 Rajab 1447 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-004
- Project
- Converting the Current Headquarters into a Member Services Centre & Committee Rooms
- Portfolio
- Building Rehabilitation & Sustainability Portfolio
- Sector
- Support Services Sector
- Sponsor
- Sarah A. Al-Qarni
- Project manager
- Eng. Waleed O. Al-Juhani
1The change
- TitleAuto-filled
- Add a wing of sectoral committee rooms
- KindAuto-filled
- Scope
- Requested byAuto-filled
- Eng. Waleed O. Al-Juhani
- Raised onAuto-filled
- 2026-01-18
Reason
A directive to provide sectoral committee rooms at HQ once the 19th-cycle committees are active
Justification
The existing rooms cannot host the 37 committees’ meetings; without the wing about a third are held off-site
2Impact analysis
Cost
SAR +1.1M
Schedule
+45 days
Risk
20 → 15
Benefits
+22%
Risk impact
The new wing is designed to Civil Defence rules from the start
Benefits impact
28 new committee rooms that host every sectoral committee meeting at HQ
3The approval decision
The PMO’s recommendation
The PMO recommends approval: the change serves the active-committees objective directly
- Change Committee decision
- Approve
- Decided on
- 2026-02-05
- Decision number
- DEC-2026-005
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & Maintenance | Submitted | — | 2026-01-18 12:33 |
| 2 | Project manager | Technical acceptance | Eng. Waleed O. Al-JuhaniProject manager | Approved | — | 2026-01-19 14:47 |
| 3 | PMO review & impact analysis | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2026-01-20 09:54 |
| 4 | Financial impact | Financial approval | Munirah A. Al-KhalidiFinance | Approved | — | 2026-01-21 13:52 |
| 5 | Contractual impact | Financial approval | Mazen A. Al-HazmiProcurement & contracts | Approved | — | 2026-01-25 14:29 |
| 6 | Change Committee | Technical acceptance | Dr. Mohammed I. Al-SubaieChange Committee | Approved | — | 2026-01-26 12:15 |
| 7 | Projects Steering Committee | Technical acceptance | Dr. Abdullah S. Al-QahtaniStrategy & Projects Steering Committee | Approved | — | 2026-01-27 09:30 |
Signatures
Project manager
Eng. Waleed O. Al-Juhani
Approved2026-01-19
PMO review & impact analysis
Ghada A. Al-Shahrani
Approved2026-01-20
Financial impact
Munirah A. Al-Khalidi
Approved2026-01-21
Contractual impact
Mazen A. Al-Hazmi
Approved2026-01-25
Change Committee
Dr. Mohammed I. Al-Subaie
Approved2026-01-26
Projects Steering Committee
Dr. Abdullah S. Al-Qahtani
Approved2026-01-27