Converting the Current Headquarters into a Member Services Centre & Committee Rooms
Remove from watchlistRebuilding the current headquarters after the move and adding a new wing with 28 rooms for the sectoral committees and meetings, and a modern members’ service hall.
Budget (BAC)
Actual cost
81% of budget
Progress
Estimate at completion
SAR +3.9M
SPI · CPI
Forecast finish
126 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 July 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-08-05 | 2024-11-17 | +104 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-01-09 | 2025-07-11 | +183 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-09-02 | 2026-07-01 | +302 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-04-26 | 2027-02-16 | +296 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-09-30 | 2027-03-08 | +159 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Late | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
68%Awaiting acceptance
9%Not handed in
23%Deliverable flow
Display options
| Project plan & baseline004-D1 | 3% | CRT-004-01 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Eng. Bandar M. Al-Shammari | 2024-05-19 | V1 | 3 of 3 |
| Monitoring & reporting004-D2 | 3% | CRT-004-02 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2024-08-05 | V1 | 3 of 3 |
| Detailed design004-D3 | 6% | CRT-004-03 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2024-10-23 | V1 | 3 of 3 |
| Permits & approvals004-D4 | 6% | CRT-004-04 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-01-09 | V1 | 3 of 3 |
| Site works & excavation004-D5 | 13% | CRT-004-05 | Approved | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-03-29 | V1 | 3 of 3 |
| Structure004-D6 | 13% | CRT-004-06 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-06-16 | V1 | 3 of 3 |
| Finishes004-D7 | 13% | CRT-004-07 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-09-02 | V1 | 3 of 3 |
| Supply004-D8 | 11% | CRT-004-08 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@chamber.sa | Eng. Bandar M. Al-Shammari | 2025-11-20 | V1 | 3 of 3 |
| Installation004-D9 | 9% | — | Submitted | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-02-06 | V1 | 1 of 3 |
| Testing & commissioning004-D10 | 9% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-04-26 | V0 | 0 of 3 |
| Provisional acceptance004-D11 | 7% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & General ServicesP-013b.alshammari@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-07-13 | V0 | 0 of 3 |
| Final acceptance004-D12 | 7% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesP-012s.alqarni@chamber.sa | Eng. Bandar M. Al-Shammari | 2026-09-30 | V0 | 0 of 3 |
| Total · 12 | 100% |