Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-007Critical4ExecutionConstructionStalled

Training & Employment Centre Complex

Remove from watchlist

A 92,000 m² complex with 42 training rooms, practical labs and a job-fair hall, ending the lease of 9 training venues.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 32M

Actual cost

SAR 22.2M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 39M

SAR +7M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Periodic update — August 2026

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Periodic update card

Progress, status, risks and support requested

Form no.
RC-PMO-F07
Template edition
2.2
Version
V1
Form date
⁦2026-09-02⁩
Hijri
20 Rabiʻ I 1448 AH
ApprovedUPD-007-2026-08Periodic update — August 2026

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
Training & Employment Centre Complex
Portfolio
Branches, Service & Training Centres Portfolio
Sector
Training & Employment Centre
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1ProgressAuto-filled

From the live data: accepted deliverables, the schedule and finance on the period’s last day.

Actual progress

⁦51%⁩

Planned to date

⁦72%⁩

SPI

0.72

Actual cost

SAR 19.6M

Main achievements this periodFilled by the project manager

Work went to the approved plan for the period, with the due deliverables handed in.

2Status

Overall healthAuto-filled
Critical
StageAuto-filled
Execution
Forecast finishAuto-filled
⁦2027-06-01⁩

The PM’s comment on the statusFilled by the project manager

The variance from the baseline stands because of late integrations; the corrective plan is running and followed weekly.

3Risks and impedimentsAuto-filled

CodeRiskScoreOwner
RSK-0026Contractor financial claims piling up over unapproved variations20Eng. Shahad M. Al-Malki
RSK-0027Late delivery of curtain-wall glazing from the overseas factory16Eng. Shahad M. Al-Malki
RSK-0028Possible removal of the MEP subcontractor15Eng. Abdulrahman S. Al-Harbi
CodeImpedimentSeverity
ISS-0109Façade works stopped — samples not approvedCritical
ISS-0110Skilled-labour shortage at the MEP subcontractorHigh
ISS-0111Dispute over the pricing of variation order 7High
ISS-0112Decision on payment certificate 25 delayedMedium

4Support requested

What the project needs from leadership or the committeesFilled by the project manager

Approve change request CR-2026-012 for three integration engineers (SAR 49K), and the Secretary-General to press the NIC on the Nafath environment.

Includes financial supportAuto-filled
Yes

Approval logChain: Periodic update approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesSubmitted—⁦2026-09-02⁩ 09:30
2PMO checkMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedThe reading agrees with the schedule and finance.⁦2026-09-03⁩ 09:06
3Sponsor review & approvalTechnical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2026-09-07⁩ 10:13

Signatures

PMO check

Ghada A. Al-Shahrani

Approved⁦2026-09-03⁩

Sponsor review & approval

Eng. Turki A. Al-Anazi

Approved⁦2026-09-07⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F07 · version V1

Periodic update card

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Periodic update approval · version ⁦1⁩

Submitted by Eng. Shahad M. Al-Malki on ⁦2026-09-02⁩

  1. Methodology review

    PMO check

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-09-03⁩ at ⁦09:06⁩

    The reading agrees with the schedule and finance.

  2. Technical acceptance

    Sponsor review & approval

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2026-09-07⁩ at ⁦10:13⁩

Steps that do not apply to this record

  • Financial support requested — the condition «Financial link?» does not hold

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-09-02⁩

    The card as the PM filled it

    Eng. Shahad M. Al-Malki

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close