PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-05-17⁩
Hijri
30 Dhuʻl-Qiʻdah 1447 AH
ApprovedCRT-012-04Benchmarking

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Institutional Performance Measurement & Power BI Dashboards
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Strategy & Institutional Excellence
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1The deliverableAuto-filled

DeliverableAuto-filled
Benchmarking
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Dr. Mohammed I. Al-Subaie
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦10%⁩
DueAuto-filled
⁦2026-04-03⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-012_2.2_v1.pdfV1Dr. Mohammed I. Al-Subaie⁦2026-02-18⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Dr. Amal F. Al-Sudairi
Accepted byAuto-filled
Dr. Mohammed I. Al-Subaie
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
—
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceSubmitted—⁦2026-02-18⁩ 10:25
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-02-23⁩ 10:07
3Inspection & technical acceptance — ownerTechnical acceptanceDr. Mohammed I. Al-SubaieProject ownerOn behalf of Dr. Amal F. Al-SudairiApprovedInspected and accepted against the approved acceptance criteria.⁦2026-02-26⁩ 11:14
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-03-01⁩ 13:04
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-03-03⁩ 14:41

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2026-02-23⁩

Inspection & technical acceptance — owner

Dr. Mohammed I. Al-Subaie

Approved⁦2026-02-26⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2026-03-01⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2026-03-03⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Dr. Mohammed I. Al-Subaie on ⁦2026-02-18⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-02-23⁩ at ⁦10:07⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Dr. Amal F. Al-Sudairi · Project owner

    Approved · ⁦2026-02-26⁩ at ⁦11:14⁩ · On behalf of Dr. Amal F. Al-Sudairi (Dr. Mohammed I. Al-Subaie)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-03-01⁩ at ⁦13:04⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-03-03⁩ at ⁦14:41⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-02-18⁩

    PRJ-2026-012_2.2_v1.pdf

    Dr. Mohammed I. Al-Subaie

Only one version so far.