PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
RC-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-10-02⁩
Hijri
10 Rabiʻ II 1447 AH
ApprovedPRJ-2026-012Institutional Performance Measurement & Power BI Dashboards

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Institutional Performance Measurement & Power BI Dashboards
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Strategy & Institutional Excellence
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-09-07⁩

Baseline finish

⁦2026-12-31⁩

Forecast finish

⁦2026-12-24⁩

SPI

1.01

MilestonePlannedForecastSlip
Project plan approved⁦2026-01-03⁩⁦2026-01-27⁩+24 days
Designs approved⁦2026-04-03⁩⁦2026-05-17⁩+44 days
Build complete⁦2026-07-03⁩⁦2026-09-03⁩+62 days
Testing & acceptance complete⁦2026-10-01⁩⁦2027-01-03⁩+94 days
Final handover⁦2026-12-31⁩⁦2027-01-23⁩+23 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦5%⁩⁦2025-11-18⁩Tariq S. Al-Yami
Monitoring & reporting⁦5%⁩⁦2026-01-03⁩Dr. Amal F. Al-Sudairi
Current-state assessment⁦10%⁩⁦2026-02-17⁩Dr. Amal F. Al-Sudairi
Benchmarking⁦10%⁩⁦2026-04-03⁩Dr. Mohammed I. Al-Subaie
Target model⁦16%⁩⁦2026-05-19⁩Dr. Mohammed I. Al-Subaie
Roadmap⁦15%⁩⁦2026-07-03⁩Tariq S. Al-Yami
Wave 1⁦15%⁩⁦2026-08-17⁩Tariq S. Al-Yami
Wave 2⁦14%⁩⁦2026-10-01⁩Dr. Amal F. Al-Sudairi
Knowledge transfer⁦5%⁩⁦2026-11-16⁩Dr. Amal F. Al-Sudairi
Final report⁦5%⁩⁦2026-12-31⁩Dr. Mohammed I. Al-Subaie
Accepted with a certificate⁦76%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
No risks recorded

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyTariq S. Al-Yami
Project ownerDeliverable status and acceptance datesFortnightlyTariq S. Al-Yami
PMOData and indicator updatesWeeklyTariq S. Al-Yami
BeneficiariesWhat changes and whenAt each milestoneTariq S. Al-Yami
Team memberRoleAllocation
Tariq S. Al-YamiProject manager⁦60%⁩
Dr. Amal F. Al-SudairiProject owner⁦20%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Tariq S. Al-YamiHead, Institutional Performance & QualitySubmitted—⁦2025-10-02⁩ 13:40
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2025-10-05⁩ 09:12
3Technical acceptance — project ownerTechnical acceptanceDr. Amal F. Al-SudairiProject ownerApproved—⁦2025-10-07⁩ 10:19
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-10-09⁩ 14:35
5Sponsor approvalTechnical acceptanceDr. Mohammed I. Al-SubaieProject sponsorApproved—⁦2025-10-13⁩ 13:40

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2025-10-05⁩

Technical acceptance — project owner

Dr. Amal F. Al-Sudairi

Approved⁦2025-10-07⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2025-10-09⁩

Sponsor approval

Dr. Mohammed I. Al-Subaie

Approved⁦2025-10-13⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Tariq S. Al-Yami on ⁦2025-10-02⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-10-05⁩ at ⁦09:12⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Dr. Amal F. Al-Sudairi · Project owner

    Approved · ⁦2025-10-07⁩ at ⁦10:19⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-10-09⁩ at ⁦14:35⁩

  4. Technical acceptance

    Sponsor approval

    Dr. Mohammed I. Al-Subaie · Project sponsor

    Approved · ⁦2025-10-13⁩ at ⁦13:40⁩

Steps that do not apply to this record

  • Plan aligned with the contracts — the condition «Contract link?» does not hold

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-10-02⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Tariq S. Al-Yami

  2. V1Returned for edit⁦2025-09-18⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Tariq S. Al-Yami