Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Closure readiness

Closure planned after the forecast finish on ⁦2026-12-24⁩

A preview of what closure will need, with the planned dates, and the lessons captured so far.

0/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedNot started

    Final acceptance of every deliverable

    Dr. Amal F. Al-SudairiPlanned ⁦2026-12-14⁩

  2. 2

    Financial closureNot started

    Spend reconciled, commitments closed

    Khalid N. Al-MutairiPlanned ⁦2027-01-13⁩

  3. 3

    Contract closureNot started

    Contracts closed, retention released

    Khalid N. Al-MutairiPlanned ⁦2027-01-23⁩

  4. 4

    Documents archivedNot started

    Documents archived with classification

    Tariq S. Al-YamiPlanned ⁦2027-01-18⁩

  5. 5

    Lessons learnedNot started

    Lessons-learned session

    Tariq S. Al-YamiPlanned ⁦2027-01-08⁩

  6. 6

    Benefits owner assignedNot started

    Benefits handed to their owner with a measurement plan

    Dr. Amal F. Al-SudairiPlanned ⁦2027-01-03⁩

  7. 7

    Final report approvedNot started

    Final report and its approval

    Tariq S. Al-YamiPlanned ⁦2027-01-28⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

The review comes after closure

About three months after the forecast finish (⁦2026-12-24⁩), with the sponsor and the benefits owner.

Lessons learned

0 lessons — offered automatically to similar projects when they are created.

Knowledge base

No lessons captured yet

Capture what the team learned during delivery; closure needs at least one.

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.

No benefits recorded for this project.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close