PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+23⁩ days vs approved

Baseline (original = approved)⁦2026-12-31⁩
Current forecast⁦2027-01-23⁩
By earned schedule⁦2027-05-16⁩
Critical activities
4
of ⁦5⁩ open activities
Late activities
3
past their baseline finish
Schedule performance
0.79
earned ÷ planned value
Next milestone
in 67 days
Testing & acceptance complete
Expand allCollapse all
Activity
Institutional Performance Measurement & Power BI DashboardsPlanned: ⁦2025-09-07⁩ → ⁦2026-12-31⁩Forecast: ⁦2025-09-07⁩ → ⁦2027-01-23⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-09-07⁩ → ⁦2026-01-03⁩Actual: ⁦2025-09-07⁩ → ⁦2026-01-27⁩
Project plan & baselinePlanned: ⁦2025-09-07⁩ → ⁦2025-11-18⁩Actual: ⁦2025-09-07⁩ → ⁦2025-12-04⁩
Monitoring & reportingPlanned: ⁦2025-10-22⁩ → ⁦2026-01-03⁩Actual: ⁦2025-11-01⁩ → ⁦2026-01-27⁩
Project plan approvedPlanned: ⁦2026-01-03⁩ → ⁦2026-01-03⁩Actual: ⁦2026-01-27⁩ → ⁦2026-01-27⁩Project plan approved
DiagnosisPlanned: ⁦2025-12-07⁩ → ⁦2026-04-03⁩Actual: ⁦2025-12-26⁩ → ⁦2026-05-17⁩
Current-state assessmentPlanned: ⁦2025-12-07⁩ → ⁦2026-02-17⁩Actual: ⁦2025-12-26⁩ → ⁦2026-03-23⁩
BenchmarkingPlanned: ⁦2026-01-21⁩ → ⁦2026-04-03⁩Actual: ⁦2026-02-18⁩ → ⁦2026-05-17⁩
Designs approvedPlanned: ⁦2026-04-03⁩ → ⁦2026-04-03⁩Actual: ⁦2026-05-17⁩ → ⁦2026-05-17⁩Designs approved
DesignPlanned: ⁦2026-03-07⁩ → ⁦2026-07-03⁩Actual: ⁦2026-04-14⁩ → ⁦2026-09-03⁩
Target modelPlanned: ⁦2026-03-07⁩ → ⁦2026-05-19⁩Actual: ⁦2026-04-14⁩ → ⁦2026-07-11⁩
RoadmapPlanned: ⁦2026-04-21⁩ → ⁦2026-07-03⁩Actual: ⁦2026-06-08⁩ → ⁦2026-09-03⁩
Build completePlanned: ⁦2026-07-03⁩ → ⁦2026-07-03⁩Actual: ⁦2026-09-03⁩ → ⁦2026-09-03⁩Build complete
ImplementationPlanned: ⁦2026-06-06⁩ → ⁦2026-10-01⁩Forecast: ⁦2026-07-21⁩ → ⁦2027-01-03⁩Float: ⁦0⁩d
Wave 1Planned: ⁦2026-06-06⁩ → ⁦2026-08-17⁩Actual: ⁦2026-08-02⁩ → ⁦2026-10-26⁩
Wave 2Planned: ⁦2026-07-21⁩ → ⁦2026-10-01⁩Forecast: ⁦2026-07-21⁩ → ⁦2027-01-03⁩Float: ⁦0⁩dDrag to change its duration+94
Testing & acceptance completePlanned: ⁦2026-10-01⁩ → ⁦2026-10-01⁩Forecast: ⁦2027-01-03⁩ → ⁦2027-01-03⁩Float: ⁦20⁩dDrag to change its datesTesting & acceptance complete
Handover & knowledge transferPlanned: ⁦2026-09-04⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-28⁩ → ⁦2027-01-23⁩Float: ⁦0⁩d
Knowledge transferPlanned: ⁦2026-09-04⁩ → ⁦2026-11-16⁩Forecast: ⁦2026-12-28⁩ → ⁦2027-01-13⁩Float: ⁦0⁩dDrag to change its dates+58
Final reportPlanned: ⁦2026-10-20⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-07⁩ → ⁦2027-01-23⁩Float: ⁦0⁩dDrag to change its dates+23
Final handoverPlanned: ⁦2026-12-31⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-23⁩ → ⁦2027-01-23⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦21⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦5⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦3⁩ activities with no float

Every day lost on this chain is a day lost at launch. ⁦1⁩ more activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Wave 2” needs a pace ⁦19.6⁩× faster than it has kept

It earned ⁦7%⁩ in 99 days; the forecast assumes the rest in 67 days. At the pace so far it finishes on ⁦2030-06-04⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 49 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

24
44
62
94
23
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Near-critical