PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Riyadh Chamber of Commerce & Industry

Project charter

Institutional Performance Measurement & Power BI Dashboards

APPROVEDV2Approved ⁦2025-09-05⁩

1Project identity

Required at this stage
Project name
Institutional Performance Measurement & Power BI Dashboards
Project code
PRJ-2026-012
Project sponsor
Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieExecutive Director, Strategy & Institutional ExcellenceP-009m.alsubaie@chamber.sa
Project manager
Tariq S. Al-YamiTariq S. Al-YamiHead, Institutional Performance & QualityP-040t.alyami@chamber.sa
Project owner
Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & the PMOP-015a.alsudairi@chamber.sa
Portfolio & programme
Institutional Excellence & Capability PortfolioInstitutional Excellence & Capability Programme
Type & methodology
Transformation · Agile
Current phase
4Execution

2Background & rationale

Required at this stage

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

3Objectives

Required at this stage
  1. 1Streamlined governance and dependable technology

4Scope

Required at this stage

In scope

  • The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.
  • As-is and to-be analysis
  • Change management plan

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1As-is and to-be analysis
  2. 2Change management plan
  3. 3Adoption measures

6Deliverables

Required at this stage
1Project management plan⁦2025-09-26⁩
2Main deliverable — stage 1⁦2026-05-10⁩
3Main deliverable — final stage⁦2026-10-25⁩
4Final report⁦2026-12-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-09-05⁩
  2. Contract signed⁦2025-11-23⁩
  3. 50% of works complete⁦2026-05-10⁩
  4. Provisional acceptance⁦2026-11-23⁩
  5. Closure⁦2026-12-31⁩

8Budget

Required at this stage
  • Main contract⁦72.4%⁩355K
  • Supervision & consulting⁦13.3%⁩65K
  • Internal team⁦9.2%⁩45K
  • Contingency reserve (⁦5%⁩)⁦5.1%⁩25K
The owning sector’s approved budgetTotal490K

9Timeline

Required at this stage
Start
2025-09-0715 Rabiʻ I 1447 AH
Baseline finish
2026-12-3122 Rajab 1448 AH
Duration
⁦16⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly