PRJ-2026-012On track4ExecutionAgileIn progress

Institutional Performance Measurement & Power BI Dashboards

Add to watchlist

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Budget (BAC)

SAR 490K

Actual cost

SAR 372K

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 490K

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
RC-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-09-05⁩
Hijri
13 Rabiʻ I 1447 AH
ApprovedPRJ-2026-012Institutional Performance Measurement & Power BI Dashboards

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Institutional Performance Measurement & Power BI Dashboards
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Strategy & Institutional Excellence
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1Objective

Background

The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.

Project objectives

  1. Streamlined governance and dependable technology

2Scope

In scope

  • The chamber’s KPIs automated down to department level on Power BI and tied to the operational plans and measurement cycles in Munjaz.
  • As-is and to-be analysis
  • Change management plan

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-09-26⁩
Main deliverable — stage 1⁦2026-05-10⁩
Main deliverable — final stage⁦2026-10-25⁩
Final report⁦2026-12-31⁩
MilestoneDate
Charter approved⁦2025-09-05⁩
Contract signed⁦2025-11-23⁩
50% of works complete⁦2026-05-10⁩
Provisional acceptance⁦2026-11-23⁩
Closure⁦2026-12-31⁩

4RolesAuto-filled

SponsorAuto-filled
Dr. Mohammed I. Al-Subaie
Project ownerAuto-filled
Dr. Amal F. Al-Sudairi
Project managerAuto-filled
Tariq S. Al-Yami
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 355K
Supervision & consultingSAR 65K
Internal teamSAR 45K
Contingency reserve (5%)SAR 25K
Approved budgetSAR 490K

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Tariq S. Al-YamiHead, Institutional Performance & QualitySubmitted—⁦2025-08-27⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2025-08-30⁩ 12:30
3Project ownerTechnical acceptanceDr. Amal F. Al-SudairiProject ownerApproved—⁦2025-09-02⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-09-03⁩ 11:10
5Sponsor approvalTechnical acceptanceDr. Mohammed I. Al-SubaieProject sponsorApproved—⁦2025-09-05⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2025-08-30⁩

Project owner

Dr. Amal F. Al-Sudairi

Approved⁦2025-09-02⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2025-09-03⁩

Sponsor approval

Dr. Mohammed I. Al-Subaie

Approved⁦2025-09-05⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Tariq S. Al-Yami on ⁦2025-08-27⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2025-08-30⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Dr. Amal F. Al-Sudairi · Project owner

    Approved · ⁦2025-09-02⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-03⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Dr. Mohammed I. Al-Subaie · Project sponsor

    Approved · ⁦2025-09-05⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-09-05⁩

    Approved version

    • PMO comments addressed

    Tariq S. Al-Yami

  2. V1Returned for edit⁦2025-08-17⁩

    First draft

    • Returned to detail the budget

    Tariq S. Al-Yami